# KEFI Gold and Copper finalises finance package for Tulu Kapi project development

- Link: https://www.directorstalkinterviews.com/kefi-gold-and-copper-finalises-finance-package-for-tulu-kapi-project-development/4121214505
- Published: 2025-09-02T07:17:37+01:00
- Author: Amilia Stone

**KEFI Gold and Copper Plc** ([LON:KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
a gold and copper exploration and development company focused on the Arabian-Nubian
Shield with a pipeline of projects in the Federal Democratic Republic of Ethiopia,
and the Kingdom of Saudi Arabia, has provided an update on the Tulu Kapi Gold Project
preparations for full Project development.

**Highlights**

·    US$340 million Project capital budget updated from 2023, being certified.

·    US$240 million expanded debt facility now formally offered by both co-lenders.

·    US$100 million equity-risk capital assembled at subsidiary level for finalisation.

·    Approvals and signing of full Project finance package scheduled for completion
in September 2025.

·    Field activities on schedule and full development expected to begin in October
2025.

**Recent Project Developments**

·    _Debt capital approval:_ The Co-lenders have now formally offered an expanded
US$240 million loan facility. Facility documentation is in circulation for signing.

·    _Approval of the Project finance package:_

o  KEFI, its main Project contractors and relevant Ethiopian Government agencies
have signed or approved definitive Project contracts that are now subject only to
lender approval. These contracts cover plant and infrastructure construction, provision
of power, new roads and long-term mining capability.

o  Establishment of a new Ethiopian holding company, KME Ethiopia Holdings being
completed.

o  Meetings with co-lenders and respective legal teams have started with a view 
to signing facility documentation by the end of September 2025.  

·    _Finalising capital requirements:_ The net increase in capital requirements
since the last estimate in 2023 has been kept to 6%, i.e. from c.US$320 million 
to c.US$340 million. This remains subject to certifications by various parties which
are currently underway. On this basis, the equity-risk capital needed is c.US$100
million (being total capital of c.US$340 million less confirmed US$240 million debt
package).

·    _Project economics:_ the life-of-mine projected operating metrics remain consistent
with recent guidance, including all-in sustaining costs (AISC) of c.US$1-1,100/oz
and first full year production of 160koz from the open pit. Annual production is
planned to then increase with the introduction of initial underground production.
Year 1 net operating cash flow is projected at c.US$200 million at a US$2,500/oz
gold price and c.US$300 million at a US$3,500/oz gold price, from the open pit with
processing at nameplate capacity.

·    _Approvals of equity-risk capital for Project development:_ All KEFI Group 
boards have directed that equity arrangements be completed this month in accordance
with the following guidelines:

o  sources of the c.US$100 million equity capital to be primarily at the Ethiopian
subsidiary level, directed particularly to long term investors experienced in African
mining generally or Ethiopia specifically and, in particular, from the Ethiopian
public and private sectors

o  The following equity has already been invested or committed in the ordinary share
capital of TKGM:

§ US$20 million by the Government of Ethiopia and being spent by the Government.

§ c.US$10 million already spent by KEFI as part of the major development works program
in addition to the pre-development historical spending of c.US$100 million.

§ c.US$10 million of KEFI share participation post-closing in respect of closing
fees and costs.

§ Relative TKGM ownership for KEFI and for the Ethiopian Government is based on 
the 2017 agreements and the consequential entry-valuation of c.US$200 million (c.
£150 million). Three agencies of the Ethiopian Government are shareholders: the 
Federal Ministry of Finance and the Sovereign Funds of both Ethiopia and the Region
of Oromia.

o  The composition of the remaining c.US$60 million is being finalised and KEFI 
has received conditional proposals which, in aggregate, exceed the required amount.
This will be finalised along the following lines:

§ An equity risk note structured as “KEFI Ethio Prefs” – a private placement to 
Ethiopian qualified investors of cumulative preference shares to be issued by the
newly-incorporated KME Ethiopia Holdings – to be non-convertible, redeemable after
8 years, US$-linked and with upside to the gold price prevailing at the time of 
subscription.

§ An equity risk note structured as a “Gold Prepayment” or “Stream” from a mining
specialist fund to TKGM – in respect of c.2% of the 1 million oz Tulu Kapi gold 
reserves.

§ Ordinary Shares in either of these Ethiopian subsidiaries with issue-pricing based
on TKGM valuation post-financial close of the Project finance package in September
2025.

§ The breakdown and details of the finalised equity-risk capital instruments will
be published upon commitment, i.e. at completion of the signing of definitive documentation
planned for September 2025.

o  Equity drawdowns and Project procurement will commence as soon as possible after
signing.

·    _Site preparations progress on schedule:_

o  For the community:

§ The local Government agencies are implementing the ‘Resettlement Action Plan’ 
with the support of TKGM.

§ As previously reported the community compensation programme was started ahead 
of the Project development schedule.

o  For road and electricity connections:

§ The new roads from site to the bitumen highway:

·    One road is nearly complete, to provide a quicker all-weather alternative to
the existing traffic routes.

·    Start of construction within the next two months for the other new access road,
which is designed to cater for all-weather delivery of heavy loads such as plant
and mine equipment.

o  For electricity connection:

§ Procurement of major components is complete.

§ Start of construction is planned within the next two months, so that its completion
is in time for plant commissioning

o  For plant and site infrastructure:

§ Immediately after signing we will:

·    procure plant components.

·    mobilise civil works to follow resettlement.

§ all construction across the Project site is phased to follow community resettlement
which is phased accordingly and in compliance with the requisite standards.

o  For mining:

§ Procuring the mining fleet in early 2026 for delivery in early 2027.

§ Pre-production mining from mid-2027 (there is negligible overburden to remove 
in order to access the orebody).

·    _Policies, procedures and recruitment progress on schedule:_

o  Governance oversight has been in place for years via the various boards and committees,
which also draw on the Project’s panel of internationally rated independent advisers.
The co-lenders have access to all these industry specialists and have installed 
their own independent monitoring specialist advisers. 

o  Policies and procedures are being sequentially installed in accordance with the
relevant international governance standards.

o  The senior construction and production leadership team is in place and the teams
under them will keep expanding as the programme progresses to:

§ Implement the imminent full development stage, including installation of the c.
94%-recovery processing infrastructure, establishment of the eight-year c.2 g/t 
gold open pit and the associated operational readiness and start-up programmes.

§ Triggering plans for the +5g/t underground development and resource/reserve expansion,
aimed initially at doubling the current one million ounce Ore Reserve, increasing
production during the first eight to ten years to a targeted c.200,000 oz per annum
and providing a sustained high-grade underground mining contribution thereafter.

§ Mobilising to complete the previously suspended Tulu Kapi district exploration
programmes, to target extensions of the Project’s production life beyond the first
eight years. Third party interference in the Group’s rights to certain exploration
properties may require legal proceedings, the outcome of which would be uncertain
and the proceedings of which may forestall access to the relevant land.

§ Assembly of the Ethiopian exploration portfolio outside the Tulu Kapi district

> **KEFI Gold and Copper Executive Chairman,** **Harry Anagnostaras-Adams, commented:**“
> All work streams are progressing well, with the immediate priority being completion
> this month of the already in-train approval and signing process for the whole 
> Project finance package, enabling full development at Tulu Kapi – a high-grade
> and high-recovery gold mine supported by its local community and without any legacy
> issues environmentally or socially.
> “This first international project finance closing for Ethiopia results from a 
> notably collaborative effort, which has brought together hundreds of people in
> many public and private organisations at Tulu Kapi, in nearby regional centres,
> in Addis Ababa, and across multiple locations worldwide.
> “We extend our sincere appreciation to everyone involved in the current finance-
> closing activities and also to the Government agencies which over recent years
> introduced the financial reforms and regulatory waivers we requested to make this
> possible.
> “Tulu Kapi has been specially designed not just for compliance from an ESG viewpoint,
> but for alignment between international project finance practices and local stakeholders,
> including the community, all levels of Government and with leading private sector
> organisations. Local shareholders will include both the public and private sectors.
> “Coincident with Tulu Kapi’s full launch, Ethiopia is experiencing somewhat of
> a gold rush – gold exports this year so far jumped from under 10 tonnes of gold
> to over 30 tonnes. Tulu Kapi stands as a showcase gold project at the heart of
> Ethiopia’s highly prospective Nubian Shield in the Oromia Region. Every aspect
> of the Project, social, environmental, technical, operational, financial and legal,
> has been designed in line with the highest international standards.
> “What a great accomplishment after so many years of tireless persistence by our
> hard-working team, to now be fortunate enough to trigger Tulu Kapi’s full development
> at what is perhaps the early stages of a major gold market boom.”

Share on:
