# KEFI Gold and Copper confirms new discovery at the Jibal Qutman Gold Project in Saudi Arabia

- Link: https://www.directorstalkinterviews.com/kefi-gold-and-copper-confirms-new-discovery-at-the-jibal-qutman-gold-project-in-saudi-arabia/4121140054
- Published: 2024-01-30T07:23:42+00:00
- Author: Amilia Stone

**KEFI Gold and Copper Plc **([LON:KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
the gold and copper exploration and development company which has focused on the
Arabian-Nubian Shield since 2008, has provided confirmation of a new discovery, 
as well as an operational update, in respect of the Jibal Qutman Gold Project in
Saudi Arabia in the Company’s minority-owned Gold & Minerals Ltd joint venture.

**_Highlights_**

·    Satellite deposit (Asfingia) discovered with excellent grades of up to 66.6g/
t gold

·    Drilling ongoing on identified 35km mineralised strike across three contiguous
licences

·    Selection of preferred production start-up plan expected by mid-2024

**_Key Points_**

·    Having completed the 13,000m in-fill drilling programme in Q3-2023, GMCO switched
to resource expansion drilling which quickly led to the discovery of the Asfingia
satellite deposit. Asfingia drilling results include:

o JQD_232: 13.9m (12.7m estimated true width (“ETW”) at 7.9 g/t gold from 53.6m (
including 1.2m at 66.6 g/t gold).

o JQD_265: 25.5m (37.5m ETW) at 1.9 g/t gold from 86.0m (including 7.4m at 5.2 g/
t gold).

o A 350m strike length has already been established down to a depth of 75m and the
deposit remains open down-dip and along strike.

o  Drilling is ongoing to define the limits of gold mineralisation and estimate 
a Maiden Resource at Asfingia to complement the other deposits at Jibal Qutman.

·    Systematic exploration is ongoing across the 270km^(2) of the three contiguous
Jibal Qutman Gold Exploration Licences (“EL’s”) to confirm structural controls on
higher-grade gold mineralisation and identify further resource potential.

·    Previous Exploration primarily focused on an 8km section of the original Jibal
Qutman EL and the full 35km mineralised strike length will now be tested.

·    Sampling and scout drilling programmes are currently underway across multiple
targets including recent shallow alluvial mining areas and are expected to identify
further drill targets.

·    In addition to scout and infill drilling, drone surveying, geological mapping,
trenching and geophysical surveying programmes are all underway to help further 
define the structural framework of the area and assist in target delineation.

·    Two diamond drill rigs and 10 experienced Saudi based exploration geologists
are focused on Jibal Qutman Gold. Reverse circulation (“RC”) drill rigs will also
shortly join the project to further accelerate exploration.

·    KEFI’s GMCO joint venture partner, ARTAR, has agreed to fund the ongoing programme
at present (without dilution) to ensure swift progress continues whilst KEFI triggers
project launch in Ethiopia at the high-grade Tulu Kapi Gold Project. This much-appreciated
support from ARTAR reflects the strong partnership relationship and the combined
priority given to production start-up in both countries.

·    The Definitive Feasibility Study (“DFS”) on Jibal Qutman Gold is making excellent
progress and release of its conclusions is expected in mid-2024. Work is currently
focused on:

o Incorporating the results of the 13,000m infill drilling program completed in 
Q3-2023 into preliminary mine design and scheduling across a range of production
scenarios;

o Finalising metallurgical test work, which has already established potential recoveries
of 80-93% on the oxide ore (depending on grade) and circa 70% on sulphide fresh 
ore through CIL processing. Optimisation studies continue for the sulphide fresh
ore;

o GMCO Board approval of the preferred start-up plan; and

o Finalising and publishing the underlying Mineral Resource Estimate (“MRE”), maiden
Ore Reserve and DFS.

> **Harry Anagnostaras-Adams, KEFI Gold and Copper’s Executive Chairman commented:“**
> _Jibal Qutman Gold is starting to shape up its plans for production. During the
> remainder of H1 2024, we expect to report a series of steps as we simultaneously
> select our preferred production start-up plan and aggressively test our recent
> breakthroughs in the geological understanding of the mineralised system. We have
> two diamond rigs running 24/7 and RC rigs will shortly join the project._
> _“At the same time, the foot remains on the accelerator at our much larger discovery,
> the Hawiah Copper-Gold Project in the Wadi Bidah Minerals Belt, where we have 
> recently been joined as explorers by Saudi Arabia’s largest mining company, Ma’aden,
> which has been granted licences adjacent to us and quickly launched a large exploration
> programme in joint venture with Ivanhoe Electric. A separate update on Hawiah 
> will be provided, as part of the ongoing recently expanded 65,000m infill and 
> expansion drill programme._
> _“Saudi Arabia is indeed fast-tracking its mining sector and GMCO is at the forefront.
> We expect significant progress over the coming weeks and months, which will reinforce
> the value being created through GMCO’s aggressive exploration programme, for the
> past few years running at the rate of over US$20 million per annum.  _
> _“We are very pleased to have so far assembled Mineral Resources of approximately
> 5 million oz gold equivalent (KEFI beneficially 2 million oz gold equivalent) 
> in Saudi Arabia and Ethiopia and we expect this to grow as drilling continues.
> KEFI has spent a total of approximately US$64 million on these projects, which
> represents an excellent establishment cost to date of only US$32/oz Resource on
> three advanced development projects.   _
> _“We will provide further updates of material developments across both of our 
> advanced Saudi projects, as well as anything notable from work currently being
> undertaken across our portfolio of exploration licences as appropriate.”_