# KEFI Gold and Copper Co-Lenders’ Boards and Committees Approve Project

- Link: https://www.directorstalkinterviews.com/kefi-gold-and-copper-co-lenders-boards-and-committees-approve-project/4121188783
- Published: 2025-03-18T08:04:50+00:00
- Author: Jacob Brown

**KEFI Gold and Copper **([LON:KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l))
the gold and copper exploration and development company focused on the Arabian-Nubian
Shield, has reported that following the recent confirmation of credit committee 
approvals ([see announcement 11 March 2025](https://www.directorstalkinterviews.com/kefi-gold-and-copper-updates-on-tulu-kapi-financing-and-major-works/4121188471)),
the Company has now been advised that both banks have also processed Board approvals
for the Tulu Kapi project.

Therefore, both of our co-lending-banks have now received support from all their
respective committees and Boards to proceed. This is subject to formal updates of
prior approvals and to all documentation reflecting the expanded $240 million offering,
and the satisfaction of standard conditions previously reported for a transaction
of this nature (see below).

Equally important, on the ground, we can now report that the community is supporting
and agreeing to the resettlement plans and compensation surveys, as explained by
Government authorities for individual households within the large mining licence
area. This follows our earlier report on settling the first compensation sum for
the initial construction camp area.

All other preparations are on track.

**KEFI Founder and Executive Chairman, Harry Anagnostaras-Adams, commented,** “After
a decade of preparing Tulu Kapi and overcoming various external challenges, we’re
pleased to have secured Tier 1 support from the Government, industry specialists,
and financial institutions to initiate development. This comes at a time when gold
prices are at record highs, with projections indicating net cash flow surpassing
the total project finance debt of $240 million in the first year alone.

“Of course, the support of the Tulu Kapi community is by far the most important 
foundation for our Project. Their continued support is very pleasing to witness.
The community will have an important role to play in establishing Tulu Kapi as a
21^(st) century-standard gold mine and one of Ethiopia’s flagship developments.”

**KEFI Gold and Copper plc**

KEFI is focused primarily on the development of the Tulu Kapi Gold Project in Ethiopia
and its pipeline of highly prospective exploration projects in the Arabian-Nubian
Shield. KEFI targets that production at Tulu Kapi will generate cash flows for capital
repayments, further exploration and dividends to shareholders.

**Background on the Project Economic Metrics:**

Tulu Kapi has particularly robust economic metrics, based largely on lack of overburden,
high grades and high recoveries. It will be a huge boost for the community, region,
country and, of course, the Company. It has been a long time in the making, necessitating
extensive regulatory reform and completion of other sensitive behind the scenes 
preparations for this first internationally project financed mining project in Ethiopia.
It has taken much patience and support from the Government.

Development capex has been “banked” (project-financed) against the open-pit 1m oz
Ore Reserves (15.4Mt at 2.1 g/t, with pit shells, mine plans and reserves derived
using a now overly conservative gold price assumption of $1,250/oz).  The project
lenders’ base case financial model also assumes only the open pit ore is processed
at average 2Mtpa from mine output starting at 2.5Mtpa. Ore Reserves and mine plans
will be refined with in-fill-grade-control drilling during Tulu Kapi’s construction
as part of the “Operational Readiness Program”.

KEFI’s business plan goes beyond what is today “bankable”. It involves early underground
development underneath the planned open pit to establish underground drilling platforms
to extend the existing 220K oz of Indicated Resource (1.2Mt at 5.7g/t), as the deposit
is open down plunge with the last drill intercept being 90m at 2.8 g/t, within which
there are several high-grade mineable zones. KEFI’s long-standing estimate is for
potential +1Moz underground ore. KEFI’s Preliminary Economic Assessment reflects
that it will introduce initial underground production and recover approximately 
200Koz (1.5Mt at 4g/t), from already reported Indicated Resource, after mine dilution.
This will supplement the open pit ore during the first 7 production years and, by
running the plant at 2.4Mtpa, the Business Plan Model shows +7 years of production
at an average of 167Koz pa generating estimated net cash flow to shareholders over
that period of $1.1-1.6 billion, i.e. after all cash outflows and at gold prices
of $2,400-3,000/oz (representing S&P Global average consensus forecasts and current
spot). On the same basis, Production Year 1 net operating cash flow is estimated
at $231-304 million. This compares with project finance debt of $240 million.