# KEFI advances Tulu Kapi resettlement and equipment procurement

- Link: https://www.directorstalkinterviews.com/kefi-advances-tulu-kapi-resettlement-and-equipment-procurement/4121259145
- Published: 2026-08-04T07:07:14+01:00
- Author: Amilia Stone

**KEFI Gold & Copper** ([LON:KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
the gold and copper exploration and development company focussed on the Arabian-
Nubian Shield, with projects in the Federal Democratic Republic of Ethiopia and 
the Kingdom of Saudi Arabia, has announced operational updates on its Tulu Kapi 
Gold Project and its separate growth pipeline in Ethiopia and Saudi Arabia.

**Highlights**

· The Phase 1 Resettlement Action Plan at Tulu Kapi, clearing the mining licence
area for the installation of initial infrastructure, is well advanced, with 100%
of compensation agreements now completed. Preparations for the Phase 2 RAP, covering
the open pit mining and plant areas are now underway.

· Project equipment procurement continues as planned, with more than 50% of major
equipment already ordered or ready for ordering

· Contractors Lycopodium, EEP, ERA and BCM are all installing their own personnel,
subcontractors and systems at Tulu Kapi.

· Physical progress on the ground at Tulu Kapi to date includes the construction
of houses away from the mining licence area, installation of an electrical substation
and a new access road from the bitumen highway to site.

· The Tulu Kapi Charitable Endowment has started several community initiatives designed
to complement the Project and support long term local sustainable enterprises and
agricultural projects.

· All key Project milestones at Tulu Kapi are tracking on schedule, with commissioning
targeted to commence in late 2027 for full production in mid-2028 from the open 
pit and process plant.

· Development planning teams in Ethiopia and Saudi Arabia are focused on production
growth in both countries which is intended to be self-funding and a re-assembled
exploration team has started to evaluate and prioritise opportunities across now-
familiar and highly prospective geological terranes in Ethiopia and the wider region.

> **Harry Anagnostaras-Adams, Executive Chairman of KEFI, commented:**
> “Following the successful assembly of the Tulu Kapi financing arrangements for
> the open pit and process plant, our focus is firmly on Project execution and on
> closing the debt drawdown processes. Progress across community resettlement, plant
> procurement and construction sub-contractor tendering is in line with schedule.
> We have developed strong working relationships with Government, local communities,
> and our international financing and contracting partners.
> “Whilst global markets have been volatile for our sector, in particular since 
> the start of the Iran War, our implementation programme remains on track. We are
> well-positioned and we continue to work closely with all stakeholders to deliver
> Ethiopia’s first modern, internationally financed gold mine. We are also advancing
> development plans for self-funded production growth at Tulu Kapi and in the minority-
> owned portfolio in Saudi Arabia, and to establish a platform for a portfolio of
> projects across Ethiopia and the region.”

**Tulu Kapi Update**

Development remains in accordance with the approved Project schedule. Activity this
month has centred on community resettlement and plant procurement, with the following
additional progress to report since the Project update announced on 26 May 2026:

· Phase 1 of the RAP, covering the airstrip, plant site, electrical substation and
construction camp, is substantially advanced: 100% of compensation agreements with
affected landholders are now completed, and approximately 90% of compensation payments
have been made; the permanent replacement housing programme is underway, with initial
accommodation arranged where required.

· Phase 2 RAP preparation has now begun including areas required for pre-production
drilling and mining.

**Plant procurement and construction sub-contractor tendering:**

· Over 50% of major plant equipment is now ordered or ready for order in line with
the disbursement schedule, including the SAG (semi-autogonous grinding) mill, vibrating
grizzly, cyclones, apron feeders, compressors and blowers, jaw crusher, agitators,
carbon regen kiln, sludge pan filters, electrowinning cells, strip solution, goldroom
furnace, goldroom safe, vault door, water treatment plant, sewage treatment plant,
intertank screens, wet vibrating screens, centrifugal and axial fans, acid wash 
and eluate filters, and drying oven.

· Principal contractors Lycopodium, EEP, ERA and BCM are now intensively mobilising
personnel, subcontractors and systems on the ground. Physical construction to date
comprises house-building for resettlement, installation of an electrical substation
and the new access road.

· The Tulu Kapi Charitable Endowment launched its first community initiatives, including
plant nurseries to support the Project’s rehabilitation programmes and local agricultural
projects, with a focus on aligning stakeholders behind maintaining the development
schedule.

· Project debt drawdown remains on track for a Q4 2026 trigger, with final timing
being optimised around disbursement scheduling and currency flows.

· Ahead of Project debt drawdown next quarter, KEFI remains well funded following
the equity capital raised in H1 2026.

**GMCO Update (13%-owned by KEFI)**

· Development sequencing starts with Jibal Qutman Stage 1 (oxide open pit), likely
to be followed by Hawiah Stage 1 (oxide open pit), and then by sulphide development
at Jibal Qutman Stage 2 and/or sections of the Hawiah system.

· Jibal Qutman’s final investment decision is targeted for H2 2026; KEFI will update
shareholders on the Definitive Feasibility Study outcome, the GMCO investment decision
and KEFI’s own participation decision at that time. Whatever level of ownership 
participation KEFI elects, the growth of production in Saudi Arabia’s planned series
of mine developments targets aggregate production in gold-equivalent terms greater
than that of Tulu Kapi and the development financing thereof will be mostly from
a combination of joint venturing and self-funded growth.

· GMCO is proud to have made significant recent discoveries in the Kingdom and to
have created joint ventures with major corporations Hancock Prospecting of Australia
and Ajlan & Bros Holding of Saudi Arabia. For KEFI shareholders this represents 
a material diversification of value as well as growth opportunities, whilst KEFI
management focuses on Tulu Kapi.

**Exploration**

· KEFI has recently re-assembled a highly successful exploration team, under Jeff
Rayner, Head of Exploration, with deep experience in Ethiopia. That team is now 
evaluating and prioritising opportunities both close to Tulu Kapi and in other under-
explored but highly prospective areas. New opportunities will be judiciously advanced
whilst KEFI prioritises construction at Tulu Kapi.