# Jubilee Metals updates Strategic Investment with IRH and progress in Zambia and South Africa

- Link: https://www.directorstalkinterviews.com/jubilee-metals-updates-strategic-investment-with-irh-and-progress-in-zambia-and-south-africa/4121149425
- Published: 2024-03-28T07:22:19+00:00
- Author: Amilia Stone

**[Jubilee Metals Group](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)
plc** ([LON:JLP](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)),
a leading diversified metals processor in Africa with significant operations in 
South Africa and Zambia, has announced an update on its strategic investment with
Abu Dhabi’s International Resources Holding RSC Limited for the development of the“
Waste Rock Project” and progress with the upgrade of its Roan copper facility in
Zambia together with the continued expansion of its chrome operations.

**Highlights**

**Copper in Zambia**

·    IRH exercises right to proceed with the formation of the Joint Venture (JV)
vehicle for the implementation of the Waste Rock Project.

·    The Waste Rock Project aims to implement an initial 4 Copper processing modular
plants holding a combined feed capacity of more than 2.4 million tonnes per annum
targeting the recovery of more than 20,000 tonnes per annum of copper in concentrates
of which 30% will be attributable to Jubilee.

·    The Roan upgrade project is progressing to schedule with commissioning activities
and ramp-up expected to commence during April 2024.

·    The resource definition of Project Munkoyo has progressed with the aeromagnetic
survey having identified a large magnetic anomaly associated with the known copper
mineralisation confirmed by geochemical assays from recent trenching samples. Processing
trials have confirmed the recoverability of the copper. Jubilee targets that initial
copper ore from Project Munkoyo will be delivered to the Sable refinery from September
2024.

**Chrome & PGM’s in South Africa    **

·    Jubilee has extended its chrome tolling agreements through to February 2027,
securing a total processing feed capacity of 2.4 million tonnes per annum in relation
to fixed margin feed.

·    The construction of Thutse’s second chrome processing module, with a capacity
to produce 300,000 tonnes of chrome concentrates per annum, is on track to commence
in August 2024.

**Statement from Leon Coetzer, Jubilee CEO:**

“The expansion of our copper operations are well underway as we look to significantly
increase our copper production in the coming months on the back of the expansion
of both Roan and Sable.

I am particularly excited by the progress of our strategic relationship with IRH
as we look to jointly develop the large Waste Rock Project which holds the potential
to again demonstrate Jubilee’s unique capability of turning waste to value.

We will continue to update the market and our stakeholders on the development of
Project Munkoyo and the expansion of this portfolio of small-scale miners in Zambia
as we leverage the successes achieved at our chrome operations.

Our chrome business continues to grow with Jubilee’s renowned processing and operational
capabilities as the drivers of our success.  The continued renewal of our toll processing
agreements speaks to the acknowledgement by industry of these capabilities.”

**Copper in Zambia**

**Waste Rock Project**

The copper Waste Rock Project scope targets the processing of in excess of 260 million
tonnes of copper containing surface material.  The project targets to initially 
implement four modular processing plants holding a combined processing capacity 
of 2.4 million tonnes per annum capable of producing more than 20,000 tonnes of 
copper in concentrates per annum, commencing in Q2 CY24 of which 30% will be attributable
to Jubilee.

The copper modular processing units are similar in design to the Roan plant upgrade
which seeks to upgrade the surface material to a copper concentrate which can be
further refined to metal. The initial capital investment for the project is estimated
at US$50 million.

Jubilee and IRH entered into a binding Framework and JV agreement in December 2023
under which terms IRH will provide the capital for the implementation of the Waste
Rock Project with Jubilee appointed to implement and operate the project, subject
to due diligence and finalisation of definitive agreements. The JV attributes 70%
to IRH and 30% to Jubilee.

Under the binding Framework and Joint Venture agreement, IRH has elected to exercise
its right to form the dedicated JV through which the project will be implemented.
This follows the due diligence of the project undertaken by Jubilee which has included
both an extensive metallurgical test-program conducted at Jubilee’s development 
centre, as well as the review of both surface sampling and historical drill results
of the waste rock material and confirming the quantity of material to be in excess
of 260 million tonnes of material.  The grade of copper in the resource varies depending
on the origin of waste rock material, with Jubilee’s internally developed modular
copper units confirming the capability to successfully upgrade the material to produce
copper concentrates more than 7% Cu for further refining.

**Project Roan Upgrade  **

The delivery and assembly of the new front-end modular unit at Roan is proceeding
as per the schedule to commence commissioning and ramp-up during April 2024. The
addition of the modular unit enhances the Roan Operation’s capability to simultaneously
process multiple feed sources and expands the overall capacity of Roan to produce
up to 13 000 tonnes of copper in concentrates per annum.

**Project Munkoyo**

Project Munkoyo is located near Sable refinery, in Kapiri Mposhi district, approximately
65km east of Kabwe, with a prospect lease area of 450 hectares. Project Munkoyo 
forms part of Jubilee’s commitment in working with small scale mining opportunities
to convert the operations into sustainable long term copper operations by integrating
Jubilee’s processing and operational expertise. Jubilee holds a proven track record
of successfully converting such opportunities into large sustainable operations 
as demonstrated by the success achieved in Jubilee’s chrome operations.

The aeromagnetic survey conducted has revealed a large magnetic anomaly linked to
the previously identified copper mineralisation, further supported by geochemical
assays from trenching samples. These findings validate the presence and extension
of the existing open pit, currently spanning 400 metres, to an estimated length 
of 1 kilometre within the lease area. The progress to-date confirms the potential
to establish a mining operation of 25 000 tonnes per month of copper reef for processing
at Sable, offering formal employment and investment opportunities to the area. Jubilee
targets that initial copper ore from Project Munkoyo will be delivered to the Sable
refinery from September 2024.

Jubilee views Project Munkoyo as one of many such identified opportunities in Zambia
and targets to grow its portfolio aggressively further in partnership with the small-
scale miners.

**Chrome & PGM in South Africa**

Jubilee’s chrome and PGM business consists of two key business drivers.  This includes
the processing of third-party chrome ore at Jubilee’s Windsor and Inyoni operations
under agreed fixed margin return per tonne of chrome concentrate produced, while
Jubilee recovers the remaining PGMs and retains the majority of this benefit. In
addition, Jubilee has significantly expanded its chrome operational capacity to 
process chrome ROM materials in partnership with the holders of chrome mining rights
under an agreed earnings share model which offers Jubilee greater exposure to the
chrome market. Combined, Jubilee holds a total chrome processing capacity capable
of producing 1.45 million tonnes of chrome concentrates per annum.

Jubilee is pleased to announce it has agreed an extension to February 2027 of the
fixed margin contracts for its Windsor chrome operations.  Which combined with the
Inyoni operations has committed 2.4 million tonnes per annum of processing feed 
capacity.

Jubilee has committed to expanding its chrome operations in collaboration with the
mining right holders at Thutse, adding a second processing unit with a processing
capacity of 300,000 tonnes of chrome concentrates per year. The commissioning of
this unit is anticipated by August 2024, financed through the cash flows from existing
chrome operations.