# Jubilee Metals’ Roan to restart with new power supply agreement granted

- Link: https://www.directorstalkinterviews.com/jubilee-metals-roan-to-restart-with-new-power-supply-agreement-granted/4121184281
- Published: 2025-01-21T07:22:04+00:00
- Author: Amilia Stone

**[Jubilee Metals Group](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)
plc** ([LON:JLP](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)),
a diversified metals producer with operations in South Africa and Zambia, has announced
that regulatory approval has been granted for its new power supply agreement in 
Zambia,  with power delivery commencing on 20 January 2025. This important milestone
enables the Company to restart the Roan concentrator and ensures a stable power 
supply going forward.

The additional power supply agreement, executed with a new broad based power provider,
secures access to a distributed power base from multiple sources of generation, 
minimising the reliance on a single supply source and mitigates risks associated
with localised power network distribution limitations. The power supply has been
delivered at a cost comparable to the Company’s existing power agreement, offering
both economic and operational stability.

**Highlights:**

 * Power delivery commenced on 20 January 2025 following approval by the regulator
   under the new power agreement.
 * The additional power supply agreement is now fully operational and capable of
   meeting the complete power demands of both the Roan concentrator and the Sable
   processing plant, if required.
 * The power solution leverages a diversified network of power generation sources
   to ensure reliability and continuity of operations.
 * The company is actively preparing for the restart of the Roan concentrator, with
   copper production rates anticipated to return to target levels as operations 
   ramp up.

> **Statement from Leon Coetzer, Jubilee Metals CEO:**
> _“The Jubilee team demonstrated great resilience in overcoming the recent power
> challenges at its Zambian operations. The commencement of the additional power
> supply successfully addresses current power supply limitations that affected Roan’s
> ability to operate historically. We now turn our attention to preparing the plant
> for re-start and remain focused on delivering reliable production and operational
> resilience.”_