# Jubilee Metals Powers Forward with Copper Expansion – Zeus Capital

- Link: https://www.directorstalkinterviews.com/jubilee-metals-powers-forward-with-copper-expansion-zeus-capital/4121185982
- Published: 2025-02-07T08:09:54+00:00
- Author: Anthony Fox

**[Jubilee Metals Group](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)
Plc** ([LON:JLP](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l))
has taken decisive steps to stabilise its operations and accelerate copper production
in Zambia, according to a new research note from Zeus Capital. With a stable power
supply now secured and a significant copper material purchase agreement in place,
the company is poised for a strong comeback following recent disruptions.

### **Stable Power Supply Restored**

Jubilee was impacted by power outages in **December 2024 and early January 2025**,
which led to a temporary shutdown of its Roan concentrator. However, the company
acted swiftly to establish a new power contract, ensuring uninterrupted operations
moving forward. The company announced the update in a regulatory statement on **
21 January 2025**, highlighting its commitment to maintaining operational efficiency.

### **Boosting Copper Production with High-Grade Material**

In an effort to offset lost production, Jubilee has acquired the rights to an initial**
200,000 tonnes of high-grade copper material**, grading approximately **1.6% copper**—
more than double the grade of the waste material currently being processed. This
strategic move could secure a long-term feed supply for up to **three years**, providing
stability and improved recovery rates for its operations in Zambia.

The copper material purchase agreement will be settled via part payment from **Jubilee
Zambia**, alongside a **US$2.7 million (£2.2 million) share issuance**, equating
to **51.8 million Jubilee ordinary shares at 4.2p per share**. These shares will
be subject to a **180-day lock-in period**, demonstrating confidence in the company’s
growth strategy.

### **Roan Production Ramp-Up**

Jubilee aims to process **30,000 tonnes per month** of this high-grade material 
at Roan, leveraging its **45,000 tonnes per month capacity**. The company is also
considering accelerating throughput to the full plant capacity and extending material
purchases for a longer period. A **4-6 week test phase** will be conducted before
issuing updated full-year copper production guidance.

### **Zeus Capital’s Take**

Zeus Capital views these developments as **highly positive** for Jubilee’s growth
outlook. The research note states:
_“A positive update today with Jubilee trying
to make good and accelerate its copper production. Against a growing copper price,
this looks like a sound strategy. Our fair value remains under review.”_

Zeus estimates that Jubilee could still meet its previous production guidance for**
South Africa and Zambia**, with the potential to exceed expectations. Current projections
suggest **8.4kt of copper production for FY25**, slightly above the company’s initial
guidance of **5.9 – 7.5kt**.

### **Final Thoughts**

With power stability restored and a strategic copper acquisition in place, Jubilee
Metals is well-positioned to drive its Zambian expansion forward. As the company
moves through its **test phase and production ramp-up**, investors will be keenly
watching for updated guidance. With copper prices on the rise, Jubilee’s proactive
approach could set the stage for a strong financial performance in **2025 and beyond**.