# Jubilee Metals on track to achieve and exceed chrome guidance

- Link: https://www.directorstalkinterviews.com/jubilee-metals-on-track-to-achieve-and-exceed-chrome-guidance/4121183468
- Published: 2025-01-13T07:07:40+00:00
- Author: Amilia Stone

**[Jubilee Metals Group](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)
plc** ([LON:JLP](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)),
a diversified metals producer with operations in South Africa and Zambia, has published
its unaudited operational and project update for the half year ended 31 December
2024 (H1 FY2025).

**Highlights**

**Zambia**

§ Lost Time Frequency Injury Rate (LTFIR) of 1.00 (H1 FY2025: 0.61).

§ Copper units produced reached 1 454 tonnes (H1 FY2024: 1 683 tonnes) below the
revised half year production target of 1 800 tonnes mainly due to the impact of 
power constraints.

§ Run-of-Mine (ROM) and in process stock increased sharply as a result, reaching
approximately 1.21 million tonnes containing an estimated 8 466 tonnes of copper
units for future processing.

§ Additional power agreement executed with a new broad based power provider to supplement
the existing power supply agreement, specifically aimed at achieving steady power
supply at Roan. The agreement:

o  Secures access to a distributed power base from multiple sources of power generation
to avoid dependency on a single supply source and localised power network distribution
limitations;

o  Is expected to commence with power supply within 7 business days pending regulatory
approval; and

o  The new additional power supply is capable of supplying all of Sable and Roan’s
power demands, if required, at a power cost similar to the existing power agreement.

§ Sable refinery was able to continue operating and remains operational given its
proximity to the power producer.

§ Roan upgrade and commissioning completed reaching ramp-up throughput targets of
a combined 45 000 tonnes per month during the period before experiencing shut-downs
due to power constraints.

o  Roan was commissioned and ramped up initially using  low-grade waste materials
before targeting the switch  to feed materials containing approximate 1.5% copper(
Cu);

o  Roan was placed under care and maintenance to prioritise maintenance activities
and to avoid any risk of equipment damage due to unstable power supply; and

o  Roan will restart with the commencement of power supply under the additional 
power supply agreement.

§ Copper production at Munkoyo unaffected by power constraints:

o  Munkoyo mining on target producing in excess of 70 000 tonnes per month of ROM
ready for future processing;

o  High grade ROM at a rate of 8 000 tonnes per month exceeding 2.5% total copper,
continues to be directly refined at Sable; and

o  Pilot-scale leach trials targeting all of the ROM produced at Munkoyo have shown
exceptional results and implementation will be accelerated with final designs and
capital estimations expected by end of Q1 CY2025.

§ Copper production rates are expected to return to target on the back of the commencement
of the additional power agreements and the restart of Roan plant.

**South Africa**

§ South Africa reported a LTIFR rate of 1.45 (H1 FY2024: 2.41).

§ Chrome concentrate produced reached record highs on the back of the successful
commissioning of two further chrome processing units increasing by 35.7% to 974 
659 tonnes (H1 FY2024: 718 189 tonnes), well on track to meet and exceed full year
guidance of 1.65 million tonnes. 

§ 6E Platinum Group Metals* (PGM) produced for H1 FY2025 reached 18 435oz (H1 FY2024:
20 244oz), on track to meet full year guidance of 36 000oz.

§ The new chrome processing modules built at Thutse met design throughput during
December setting a record total chrome concentrate production for Q2 FY2025 of 519
310 tonnes.

_*  6E PGM –_ _Platinum, palladium, rhodium, ruthenium, iridium and gold_

**Production guidance for FY2025**

§ Copper: Increased copper production in place, however, guidance is under review
until such time as consistent power supply is established and Roan is brought back
into operation following the most recent agreement.

§ Chrome and PGM: On-track to achieve and exceed chrome concentrate production guidance
of 1.65 million tonnes, and PGM production guidance of 36 000oz.

> **Statement from Leon Coetzer, Jubilee Metals CEO:**
> _“Over the past quarter, we have experienced significant challenges in our Zambian
> operations brought on by a combination of extraordinary circumstances outside 
> of our direct control. We have addressed the power supply challenge by entering
> into an additional power supply agreement that  sources power across a broader
> generation network to avoid localised exposure to network instabilities and a 
> single power generation plant. This power supply contract should successfully 
> address current power supply limitations that affected Roan’s ability to operate._
> _The timing of the interruptions was particularly unfortunate given the recent
> successful commissioning of the upgraded Roan facility set to significantly increase
> the copper production alongside the Munkoyo operation. We expect to return to 
> the processing rate previously achieved at Roan once power delivery under the 
> new power supply agreement commences._
> _The Munkoyo process trials have delivered very encouraging results confirming
> our ability to process all of the ROM mined at Munkoyo on-site, at a much lower
> operating cost and a reduced operating footprint than originally envisaged. This
> offers the potential to fast track the implementation of this process solution.
> Our technical team is completing the design and implementation plan which is expected
> within this quarter._
> _While unexpected setbacks manly outside of our control do provide hurdles to 
> a smooth growth path in Zambia, we have successfully navigated these challenges
> and I remain confident in our ability to bringing full value to the investment
> made into the expansion of our operating and processing footprint. We are withholding
> an updated copper guidance until the additional power under the power agreement
> is delivered and we are able to return to running the operations on a continuous
> basis. _
> _In South Africa, the team continues to deliver an exceptional performance, and
> we are well on track to achieve and exceed our chrome guidance of 1.65 million
> tonnes of chrome concentrate for FY2025, following the two new Thutse production
> modules reaching design capacity during December, leading to a quarterly production
> record for Q2 FY2025. Our Chrome and PGM business have proactively reacted to 
> the sharp decline in the chrome market prices by successfully increasing both 
> operational efficiencies and overall throughput.”_

**Zambia**

**Half Year Production results**

The table below presents the unaudited operational production performance of Zambia
for H1  FY2025:

| **OPERATIONAL PERFORMANCE** |  | **H1 FY2025** | **H1 FY2024** | **% change** | 
| **COPPER** |  | ** ** | ** ** | ** ** | 
| **In process stock** |  |  |  |  | 
|  Copper in process stock | DMT |        1 210 312 |                 –   | 100.0% | 
|  Grade | Tcu% | 0.7% |                 –   | 100.0% | 
|  Copper units | tonnes |            8 466 |                 –   | 100.0% | 
| **Production** |  |  |  |  | 
|  Copper | tonnes |            1 454 | 1 683 | (13.6%) |

**Power supply agreement**

A new power agreement has been executed with a broad-based power provider to supplement
the existing power supply arrangement. This agreement secures access to a broader
and more distributed power base and power sources, reducing the Company’s reliance
on a single power generation facility that is vulnerable to local distribution and
generation constraints. These constraints have significantly impacted continuous
operations at the Roan facility, an issue which the supplementary agreement aims
to resolve. Power supply under the new agreement is expected to commence within 
7 business days, pending regulatory approval. The Company was successful in securing
power rates comparative to the current power rates charged under the existing power
agreement. The new agreement caters for the potential to supply all of the power
demands at both Sable and Roan if required.  

**Roan Concentrator**

The Roan upgrade and commissioning were successfully completed during the period,
with the operation achieving ramp-up targets by processing low-grade ROM from extensive
historical stockpiles. However, after reaching capacity, the Roan operation faced
significant challenges, leading to a partial closure to resolve issues related to
supplementary power agreements. Roan was placed under care and maintenance to prioritise
key maintenance activities during this period.

Roan achieved a combined throughput of 45 000 tonnes per month processing low grade
materials to minimise loss of copper during the ramp-up and commissioning of the
operation. Roan was scheduled to switch over to the longer-term feed material targeting
a copper grade in excess of 1.5% Cu prior to the forced closure. Roan is expected
to complete with the switch over once stable power under then new power agreement
is established.

**Sable Refinery**

In line with Jubilee’s ongoing resource expansion in Zambia, the Company is upgrading
Sable to serve as a dedicated facility for processing materials from Open-Pit mining
operations, including the recently acquired Munkoyo and Project G. The upgrade is
currently in progress and is expected to be completed during Q2 FY2026.

The successful acquisition of these targeted resources has enabled Jubilee to transform
Sable into a specialised refiner focused on shallow Open-Pit mining operations.

**Munkoyo**

Copper production at Munkoyo has remained unaffected by recent challenges, with 
total production of ROM exceeding 70 000 tonnes per month.  The high-grade ROM exceeding
2.5% Cu is direct leached and refined at Sable targeting a rate of 8 500 tonnes 
per month of ROM delivered. The remaining lower grade ROM at an approximate grade
of 0.7% Cu is stockpiled on site. An on-site leaching process targeting all of the
ROM mined at Munkoyo has been developed by Jubilee’s technical team with pilot trails
scheduled during the period.

The pilot-scale leach trials of Munkoyo material, initiated in December 2024, have
delivered exceptional results, demonstrating significantly reduced acid consumption
rates for copper extraction and the potential to considerably reduce the required
operating footprint. Currently, only high-grade ROM material is transported to Sable
for refining, while the remaining ROM is stockpiled at Munkoyo for further on-site
processing.

The leach trials confirm not only the recoverability of copper from the ROM, but
also the strong economic returns this processing method offers to the Munkoyo operation.
Implementation of the leach solution will be accelerated, with final design and 
capital estimates expected by the end of Q1 CY2025. Based on pilot run results, 
a modest capital investment is required at Munkoyo, with most equipment sourced 
locally to avoid long lead times. Further details will be provided as soon as possible.

**Project G**

Following the completion of Jubilee’s due diligence on Project G during August 2024,
the Company acquired a majority interest in Project G.

The project aims to expand existing operations to achieve an initial mining rate
of 10 000 tpm by February 2025. Project G includes an on-site facility designed 
to pre-concentrate mined ROM material, with an immediate capacity to produce 3 000
tonnes of copper concentrate per month, containing 10% to 15% copper. Lower-grade
copper will be stockpiled for future on-site processing. First copper concentrate
was produced at Project G during October 2024.

**Large Scale Waste Rock Project**

The project targets the processing of the approximate 260 million tonnes of previously
mined material through a dedicated processing footprint resembling the new Roan 
facility. The Company is currently focussed on the completion of the extended industrial
trial as part of its ongoing due diligence review. Under the terms of the option
to purchase agreement, a due diligence extension to the end of January 2025 has 
been agreed to allow sufficient time to compile the results from the trial.

**South Africa**

**Half Year Production results**

The table below presents the unaudited operational production performance of South
Africa for H1  FY2025:

| **OPERATIONAL PERFORMANCE** |  | **H1 FY2025** | **H1 FY2024** | **% change** | 
| **Chrome and PGM** |  | ** ** | ** ** | ** ** | 
| **Production** |  |  |  |  | 
|  Chrome | tonnes | 974 659 |        718 189 | 35.7% | 
|  PGM | Oz | 18 435 | 20 244 | (8.9%) |

The Company continues to experience growth in its South African operations, which
are now well-established and consistently delivering strong results. Chrome operations
increased output to 974 659 tonnes for H1 FY2025 on the back of improved efficiencies
while PGM production benefited from better quality feed to produce 18 435 ounces.

Construction and commissioning of the two new chrome processing modules was successfully
completed and commissioned contributing to the record production achieved over the
past period.

Share on: