# Jubilee Metals Group Renewable Power Fuels Major Milestones in Zambia

- Link: https://www.directorstalkinterviews.com/jubilee-metals-group-renewable-power-fuels-major-milestones-in-zambia/4121171505
- Published: 2024-09-23T08:30:56+01:00
- Author: Emily Johnson

**[Jubilee Metals Group](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)
plc** ([LON:JLP](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)),
a diversified metals producer with operations in Zambia and South Africa, has provided
an update on the implementation of its Copper Strategy in Zambia.  

The Zambian Copper strategy is centred around an initial processing capacity target
of 25 000 tonnes of copper per year, supported by two key operational sites: the
integrated Sable Refinery (Sable) and the upgraded Roan Concentrator (Roan). The
Company aims to fully utilise this capacity by bringing its secured copper resources
into production through open-pit mining operations and the reprocessing of surface
waste.

A crucial factor for successfully executing the Copper Strategy was securing a stable
power supply, a significant challenge in Zambia. The Company has announced that 
its recently signed power purchase agreement with Lunsemfwa Hydro Power Company (
LHPC) which has been implemented, with uninterrupted power being delivered to Jubilee’s
operations as of last week covering all of its processing plants’ power requirements
with 100% renewable power.

**Highlights**

·    Stable power supply to Zambian operations commenced after successfully implementing
the LHPC agreement on 18 September 2024.

·    Roan front-end module has achieved design capacity, and operations have been
handed over to the Roan operational team.

·    Munkoyo open-pit operations began ramping up, targeting to reach 15 000 tonnes
of run-of-mine ore per month comprising 5 000 tonnes of 3.0% high-grade copper ore
delivered direct to the Sable Refinery while the sub 1.0% lower grade copper ore
is being stockpiled at site for further processing.

·    Large Waste Rock project, with over 260 million tonnes of surface rock, is 
set to begin a commercial trial of 15 000 tonnes processed through Roan’s front-
end module in November 2024 as part of the final due diligence review.

**Leon Coetzer, CEO of Jubilee Metals Group commented:**

“I am pleased to provide this update on the progress of the implementation of our
Copper Strategy in Zambia. Establishing a stable power supply was crucial to maintaining
steady progress in our projects. The frequent rolling outages posed an ongoing risk
to the stability of our operations, so I am grateful that we have now secured a 
reliable, continuous power source. This has been a critical factor in achieving 
design throughput at our new Roan front-end module.

With upgrades at our Roan Concentrator and Sable Refinery, we are well-positioned
to achieve our initial target processing capacity of 25 000 tonnes of copper per
year. The recent milestones, including the ramp-up of our Munkoyo open-pit operation,
near completion of our due diligence of Project G, which if successful will be brought
into operation within 4 months, ensure a continued upward drive in our copper output.
Our discussions to secure a further two open pit opportunities are progressing well
and I am confident in our ability to secure further similar opportunities.

We are nearing the completion of due diligence for our Waste Rock project, with 
the distinct advantage of conducting a full-scale commercial trial using our new
Roan front-end module.

We are optimistic about the future and remain focused on bringing our secured copper
resources into production as we fully utilise our expanded processing capacity. 
I look forward to keeping the market updated on all developments as they unfold.”

**Implementation of Processing Capacity**

The increased processing capacity of 25 000 tonnes of copper per annum will be achieved
through upgrades to both the Roan Concentrator and the Sable Refinery.

The Roan Concentrator upgrade is now complete, with its front-end module reaching
design throughput of 45 tonnes per hour of waste rock feed for an 8-hour continuous
period under the supervision of the Jubilee technical team. This milestone has enabled
the handover of operations to the Roan operational team to operate the plant on 
a 24-hour continuous period.

Additionally, the commencement of stable power supply through the LHPC agreement
ensures continuous operation of Roan’s front-end module targeting to achieve 30 
000 tonnes per month feed rate.  Roan’s front-end module production is expected 
to start reflecting in the production of Q4 CY2024 as it commences to operate continuously
which is in-line with the Company’s copper production forecast.

Roan is now capable of processing both historically mined low grade stockpiled material
and previously processed materials simultaneously, with a combined capacity of its
front-end module as well as milling and flotation plant of up to 13 000 tonnes of
copper per annum (4 500 and 8 500 capacity respectively), depending on the feed 
grade. Roan will initially be dedicated to processing waste from historical mining
operations, upgrading copper materials into a saleable concentrate that can either
be sold on the market or further refined at Sable, depending on Sable’s available
capacity.

The planned Sable Refinery upgrade marks the final stage in reaching the initial
target of a combined 25 000 tonnes of copper processing capacity per annum. This
upgrade includes enhancements across several areas of the refinery, culminating 
in the commissioning of a second tank house for copper cathode plating. Upon completion,
Sable will be capable of producing both copper sulphide concentrates and copper 
cathode, with a combined output of 16 000 tonnes per annum. The upgrade is currently
underway and expected to be fully integrated into the existing operations over the
next 10 months with an expected capital investment of US$9 million, confirming the
processing capacity of 25 000 tonnes annually. The Company’s focus is now shifting
towards bringing secured copper resources into full production to fully utilise 
this upgraded capacity in line with the production forecast which assumes that the
impact of the capacity upgrades will reflect during H2 FY2025.

**Copper Resources**

**Open Pit Mining Operations**

Jubilee Metals acquired a 95% interest in the Munkoyo mine, which is located within
55 kilometres of the Sable Refinery, in June 2024 and proceeded to develop an open
pit mining operation to access the near surface weathered copper reefs. 

The Munkoyo open-pit mining operations yield high-grade copper ore, which is transported
directly to Sable, as well as lower-grade copper ore that is stockpiled on-site 
for further processing at a regional processing hub (discussed further below). The
high-grade ore, with a target copper content of 3.0%, is refined at Sable. Munkoyo
commenced operations in July 2024 and continues to ramp up to an initial target 
of 15 000 tonnes per month of run-of-mine of which 5 000 tonnes per month are to
be delivered directly to Sable for refining. Munkoyo remains on track to reach its
initial target of 15 000 tonnes per month mined run-of-mine ore by December 2024.

A resource drilling program is currently underway, and depending on the confirmation
of resource continuity, will target the potential to increase production to 20 000
to 25 000 tonnes of run-of-mine ore per month.

The decision on the capacity of the regional processing hub is currently under-review
and subject to the completion of the technical development program which is expected
to be completed over the coming 4 months. The regional hub will focus on upgrading
the mined and currently stockpiled lower grade copper reef (sub 1.0%). This material
will then be transported as a high grade copper concentrate to Sable which could
potentially double the copper output from Munkoyo delivered to Sable. This approach
would be replicated for all the open cast mining operations that Jubilee targets
for acquisition.

Project G is the second open-pit mining operation being evaluated by Jubilee. The
Company is nearing the completion of its due diligence, which has included full-
scale processing trials at the Sable Refinery. A final decision on Project G is 
anticipated by the end of September 2024. The due diligence focuses on an initial
mining rate of 10 000 tonnes per month achievable by February 2025, with an existing
on-site upgrading facility of the run-of-mine material which already can produce
3 000 tonnes of copper concentrate per month, containing 10% to 15% copper, for 
refining at Sable.  The lower grade copper reef will initially be stockpiled at 
source for future processing through the regional processing hub. 

Jubilee is also in advanced discussions regarding two additional open-pit mining
opportunities in the Munkoyo and Project G region, as it aims to fully dedicate 
Sable’s 16 000 tonne per annum copper refining capacity to processing open-pit mining
resources. Jubilee has set a goal to achieve this by December 2025.

**Previously Mined Waste Rock**

Roan has begun processing low grade stockpiled material from historical mining operations
through its newly commissioned front-end module. The module is designed to upgrade
the waste rock material more than tenfold, producing a high-grade copper concentrate
in excess of 10% copper contained for further refining or market trading. Additionally,
the plant generates a lower-grade copper stream that requires further processing.
The Jubilee technical team is currently evaluating various metal extraction techniques
to refine this waste stream, with a preference for on-site flotation and leaching.
The review includes exploring the use of glycine-based heap leaching in partnership
with Draslovka, a mining processing specialist. A semi-commercial trial for flotation
and on-site leaching of the low-grade copper stream is scheduled for February 2025.

The large Waste Rock Project, with an estimated 260 million tonnes of surface material,
is currently undergoing its final technical review. As previously announced, Jubilee
has secured the rights to the extensive waste rock stockpile, pending the successful
completion of due diligence to Jubilee’s satisfaction, in partnership with International
Resources Holding (IRH) from Abu Dhabi.

The due diligence of the copper waste rock material undertaken by Jubilee has included
various sampling campaigns as well as laboratory and pilot scale test programs to
confirm the upgradability. In parallel to the test program, Jubilee Metals entered
into agreements to accelerate delivery timelines of key long lead items.

Jubilee has reached agreement to extend the due diligence period to 6 November 2024
to accommodate the extensive test program which culminates in a full commercial 
trial of the large Waste Rock Material through the newly commissioned Roan front-
end module. It is planned to process approximately 15 000 tonnes of the material
at Roan as final confirmation of the response of the material to the proposed processing
solution. Due to the initial delays in the commissioning of Roan it is expected 
that the due diligence period will be extended to January 2025 subject to agreement
reached to ensure sufficient time to complete the commercial trial and allow the
Jubilee technical and commercial team to complete the review of the results.

To date, US$4.95 million has been advanced to secure the rights to the large Waste
Rock Project, as part of the overall acquisition price of US$30 million, payable
quarterly over 18 months, contingent on the successful completion of the due diligence
period. According to the terms of the agreement, Jubilee will forfeit the payments
made thus far if it decides not to proceed with the project. The successful completion
of due diligence is a critical factor in maintaining Jubilee’s partnership with 
IRH.

The scale of the large Waste Rock Project indicates the need for four processing
modules similar to the Roan front-end module, requiring an estimated capital investment
of around US$50 million subject to funding. Preliminary production estimates suggest
that these modules could collectively produce approximately 2 000 tonnes of copper
per month.

An accelerated construction schedule for all four modules could generate economies
of scale and significant cost reductions. The project timeline for implementing 
all four modules depends on the sequencing of their installation, but through the
establishment of strategic partnerships with the suppliers of key long lead items,
modules could be completed within a 12-month period from the commencement of construction.

The figures above serve only as indicative numbers of the potential that the resource
holds based on the assumptions and test work undertaken by Jubilee’s technical services
department and the successful completion of the due diligence which includes the
commercial trial at Roan.

**Background Information on LHPC**

LHPC is an established independent power producer in Zambia that owns and operates
two hydropower plants in the central province. LHPC is a member of the Southern 
Africa Power Pool and an active power trader in the regional market. LHPC is building
a 20MW solar plant and plans to use its portfolio of renewable power sources to 
meet Jubilee Zambia’s power requirements. The agreement highlights Jubilee’s dedication
to sustainable energy practices. The power will be supplied from an integrated solar
power and hydro-storage facility which is expected to be brought into operation 
over the coming 12 months.  Under the agreement all of the current power needs of
both Sable and Roan will be supplied via the LHPC agreement.