# Jubilee Metals Group PLC 57% increase in quarterly operational earnings

- Link: https://www.directorstalkinterviews.com/jubilee-metals-group-plc-57-increase-in-quarterly-operational-earnings/412774347
- Published: 2019-05-09T07:20:23+01:00
- Author: Giles Arbor

**[Jubilee Metals Group](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)**(
[LON: JLP](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)),
the AIM and AltX traded metals processing company, has today announced its operational
update for Q1 2019.

**Highlights**

· 57% increase in quarterly operational earnings to GBP 3.22 million (ZAR 58.85 
million)

· 54% increase in combined quarterly revenue up to GBP 6.56 million (ZAR 119.90 
million)

· PlatCro chrome acquisition completed and contributing to Company earnings ahead
of projections

· PlatCro PGM* project (platinum and palladium dominant) targeted to commence with
production in Q2 2019

· First chrome concentrate from DCM fine chrome project delivered to market with
production ramp up expected to reach full design capacity of 25 000 tonnes per month
in Q2 2019

· Exposure to wider commodity basket, including chrome, PGMs, vanadium, zinc and
lead

· Increased backing from institutional investors secured to complete funding for
the Kabwe project

· Successful secondary placement of all Jubilee shares held by BMR Group PLC to 
institutional investors

* 6 Element Platinum Group Metals including platinum, palladium, rhodium, ruthenium,
osmium and gold

 

> **Leon Coetzer, Jubilee Metals Group Chief Executive Officer, says:**
> “The period has been exceptional for Jubilee, showcasing the implementation of
> our stated mission to grow our earnings base, while maintaining strong margins
> and diversifying our operational footprint into base metals and across a number
> of mining jurisdictions.
> The team delivered strong earnings growth breaching GBP 3 million while simultaneously
> implementing the PlatCro chrome transaction to increase our chrome operational
> footprint and successfully securing the funding for the implementation of our 
> Zambian Kabwe project. This performance was achieved despite a notoriously slow
> operational period in January.
> Our DCM fine chrome project is a remarkable achievement, delivering its first 
> saleable chrome concentrate to the market. I look forward to the team achieving
> full design throughputs on the back of this success during the next period. “

**Consolidated operational financial review for Q1 2019**

Q1 2019 has seen continued delivery by the Jubilee team bringing into operation 
a further two projects, with the acquisition of the PlatCro chrome operation and
the commissioning of the DCM fine chrome project.

This strong performance is expected to continue in Q2 2019 as the PlatCro PGM project
is brought into production at a targeted processing rate of 60 000 tonnes per month
and the acceleration of the Kabwe vanadium, zinc and lead project, following the
recent acquisition of the Sable Zinc Kabwe Limited (“Sable Refinery”) refinery in
Zambia.

The table below presents the operational revenue and earnings performance for Q1
2019.

  |

####  PGM

  |

Project revenue  (GBP’000)

  |

Project revenue  (ZAR’000)^(1)

  |

Jubilee attributable earnings (GBP’000)

  |

Jubilee attributable earnings (ZAR’000)

  |  
 |

Q4 2018

  |

 3,737

  |

 68,807

  |

 2,173

  |

 40,078

  |  
 |

Q1 2019

  |

 3,443

  |

 62,959

  |

 1,908

  |

 34,993

  |

 

  |

CHROME

  |

Project revenue  (GBP’000)

  |

Project revenue  (ZAR’000)^(1)

  |

Jubilee attributable earnings (GBP’000)

  |

Jubilee attributable earnings (ZAR’000)

  |  
 |

Q4 2018

  |

 534

  |

 9,840

  |

(123)

  |

(2,267)

  |  
 |

Q1 2019

  |

 3,117

  |

 56,945

  |

 1,309

  |

 23,854

  |

 

  |

COMBINED

  |

Project revenue  (GBP’000)

  |

Project revenue  (ZAR’000)^(1)

  |

Jubilee attributable earnings (GBP’000)

  |

Jubilee attributable earnings (ZAR’000)

  |  
 |

Q4 2018

  |

4,271

  |

78,647

  |

2,049

  |

37,811

  |  
 |

Q1 2019

  |

6,560

  |

119,904

  |

3,216

  |

28,847

  |

 1 = Average monthly conversion rates used

 

**Reporting timetable going forward**

With the rapidly widening project footprint in terms of mining jurisdictions, and
commodity basket, as well as an active expansion plan, the Board has, in consultation
with a number of major shareholders, concluded that it will in future present a 
more detailed consolidated operational and financial review on a six monthly period
while continuing with a more frequent project update. As the business continues 
to mature, the Board believes this will provide shareholders with a more detailed
view of the Company’s operational and project performance.

**PlatCro operations – chrome, platinum and palladium (South Africa)**

Following completion of the acquisition of the PlatCro chrome operation in mid-January
2019, the Company has successfully phased in management and operational control 
over the project. The chrome operation has already contributed positively to the
group chrome earnings ahead of projections as the Company continues to drive efficiencies
and enhance performance.

Importantly, Q2 2019 will be the first full quarter for this operation, and a more
detailed operational and financial performance will be provided in the half yearly
update, which the Company believes will be more reflective of the potential of this
operation. The PlatCro PGM project is expected to commence with the production of
platinum and palladium rich concentrates during Q2 2019, and holds the potential
to double Jubilee’s current PGM ounce production over the life of the project.

**Hernic PGM operations – platinum and chrome (South Africa)**

The Hernic PGM operation maintained a strong performance despite the power outages
suffered during February and the delay in reaching full operational levels following
the festive period which affected the supply of feed material during January 2019.
The operations have returned to full operational levels producing in excess of 2
000 PGM ounces for April 2019.

The Company maintained the operation’s low cost base producing at below USD400 per
PGM ounce sold, to achieve an attributable project earnings for the quarter at GBP
1.91 million (ZAR 35 million).

**DCM operation – chrome (South Africa)**

Jubilee’s ground breaking DCM fine chrome recovery plant, constructed during Q4 
2018, has successfully advanced its commissioning phase during Q1 2019, with the
first chrome concentrate being produced to target concentrate grades in January 
2019 and delivered to market.

The production rate continues to be ramped up with design throughput rates of 25
000 tonnes per month expected to be reached during early Q2 2019. This new fine 
chrome recovery plant is a significant milestone for Jubilee as it demonstrates 
to the industry the recoverability of fine chrome at saleable concentrate grades.

**Kabwe operation – zinc, lead and vanadium (Zambia)**

As previously announced on 21 March 2019, Jubilee has entered into an agreement 
with two subsidiaries of [Glencore plc](https://www.directorstalkinterviews.com/ftse-company/glencore-plc/glen.l)(
[LON: GLEN](https://www.directorstalkinterviews.com/ftse-company/glencore-plc/glen.l))
to acquire Sable Zinc Kabwe Limited in Zambia.

Closing of the Acquisition is conditional upon the fulfilment of certain conditions
precedent as contained in the Agreement, including the approval of the Acquisition
under the Zambian Competition Act. Jubilee has submitted its application for the
approval of the Acquisition to the Zambian Competition and Consumer Protection Commission
and has had positive engagements with the Commission to further its review of the
application.

During this interim period, Jubilee’s project team has been granted access to the
Sable Refinery to refine the implementation plan with a view to integrating Jubilee’s
vanadium, zinc and lead refining process with the existing operations at the Sable
Refinery once the condition relating to the Approval by the Commission as noted 
above has been satisfied.

Jubilee has entered into discussions with various potential suppliers of run of 
mine zinc rich material within the Kabwe region. The supply of such high grade zinc
material offers the potential to increase the targeted zinc refining capacity in
addition to the targeted Kabwe surface material. Jubilee would only consider such
processing opportunities if they are value accretive and further enhances project
operating margins. Each of these opportunities are carefully considered both commercially
and technically by Jubilee and ranked based on potential value addition to the Kabwe
Project.

One such potential supplier of zinc ore includes Star Zinc a company in partnership
with Galileo Resources PLC. Jubilee is in discussions with Galileo to evaluate the
pre-classification at source of a high grade zinc stream which would be suitable
for further refining at Jubilee.

General

Jubilee is pleased to announce that the Company has successfully facilitated the
placement of all Jubilee shares held by BMR Group PLC (“BMR”) with a large institutional
investment fund. BMR no longer has an interest in the ordinary share capital of 
Jubilee. This relates to the 2018 transaction whereby Jubilee acquired 29.01% of
BMR as announced on 15 January 2018. The acquisition consideration at the time was
satisfied through a combination of cash and the issue of new Jubilee shares.

Share on: