# Jubilee Metals group Hernic project’s operational earnings attributable to Jubilee up 19% to GBP 1.92 million

- Link: https://www.directorstalkinterviews.com/jubilee-metals-group-hernic-projects-operational-earnings-attributable-to-jubilee-up-19-to-gbp-1-92-million/412760100
- Published: 2018-10-17T09:58:28+01:00
- Author: Charlotte Edwards

**[Jubilee Metals Group](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)**(
[LON:JLP](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)),
released quarterly operations update Q3 2018

**Highlights**

· Hernic project’s operational earnings attributable to Jubilee up 19% to GBP 1.92
million (up 28% to ZAR 35.52 million)

· Hernic PGM* production up 4% to 6 009 ounces

· PGM* production record set of 2 270 ounces in a month

· Combined operational earnings attributable to Jubilee up 8% to GBP 1.78 million(
up 16% to ZAR 32.89 million)

· Construction of fine chrome recovery plant at DCM progressing to schedule

· Targeted execution strategy for the Kabwe zinc and lead project

* 6 Element Platinum Group Metals

> **Leon Coetzer, Chief Executive Officer, says:**
> “I am very pleased to report yet another solid performance by the Jubilee team.
> I am equally excited with the traction gained in the implementation of our global
> metals recovery strategy. We have seen a growing demand from both small and global
> mining companies to work with Jubilee in accessing the metals lost in the current
> and historical mine waste.
> Our Hernic project has breached our targeted 6 000 PGM ounces produced in a single
> quarter. The project continues to increase earnings as we focus to further increase
> the feed rate to the facility. The operational costs for the project remain well
> contained, delivering a cost of less than USD400 per produced PGM ounce.
> The construction of our fine chrome recovery plant is well underway at our DCM
> plant, targeting completion by November 2018. Once completed the fine chrome recovery
> plant will target the recovery of the approximate 620 000 tonnes of chrome material
> contained in the existing DCM tailings dam alone. An initial recovery target of
> 52% has been set.
> Our Kabwe project has seen the successful conclusion of the research and design
> of the zinc recovery circuit. The new circuit design includes pre-processing of
> the surface tailings to produce an upgraded product for further leaching and refining.
> The refinery will target an initial throughput of approximately 10 000 tonnes 
> per month ramping up to an approximate 25 000 tonnes per month at completion of
> the project. The new refining circuit offers the further potential to secure future
> ore supply from current zinc explores in the region.”

**Hernic Project – Platinum and Chrome (South Africa)**

The Hernic Project delivered another stellar performance for Q3 continuing its performance
improvement quarter on quarter since commissioning. Ounces delivered breaks through
the 6 000 ounces target set for the project for the first time since the start of
production in April 2017. Hernic Project earnings increased by 28% in ZAR terms 
quarter on quarter. The project further improved on its cost base per PGM ounce 
producing below USD400 per PGM ounce. Q3 included a new record production of 2 270
PGM ounces in a single month. We expect to further increase this production rate
in line with the focussed increase in reclaimed surface material delivered by Hernic.

The table below presents the comparative quarterly performance of the Hernic project:

  |   |

Tailings processed tonnes

  |

PGM ounces delivered

  |

Project revenue  (GBP’000)^(1)

  |

Project revenue  (ZAR’000)^(2)

  |

Project earnings^(3)(GBP’000)

  |

Project earnings (ZAR’000)

  |

Jubilee attributable earnings (GBP’000)

  |

Jubilee attributable earnings (ZAR’000)

  |

Unit cost / PGM oz (USD)^(4)

  |  
 |

Total Q1 2018

  |

110 409

  |

4 897

  |

2,651

  |

44,013

  |

1,141

  |

18,908

  |

1,141

  |

18,908

  |

434

  |  
 |

Total Q2 2018

  |

119 479

  |

5 800

  |

3,308

  |

56,761

  |

1,612

  |

27,686

  |

1,612

  |

27,686

  |

397

  |  
 |

Total Q3 2018

  |

 135 146

  |

 6 009

  |

 3 356

  |

 61,785

  |

 1,920

  |

 35,523

  |

 1,920

  |

 35,523

  |

 311

  |  
 |

Project to date

  |

673 178

  |

24 141

  |

13,361

  |

233,755

  |

6,024

  |

106,247

  |

6,024

  |

106,247

  |

407

  |

 

1= Revenue from the current project phase – 100% attributable to Jubilee until full
capital recovery. Revenue is projected based on latest      average PGM market prices
and USD exchange rates and results are only final once final Quotational Period 
has passed

2= Average monthly conversion rates used

3= Project Earnings include all incurred operational costs including management 
services and mineral royalties

4= Unit cost includes provision for utility overhead.

**DCM Project – Chrome (South Africa)**

The construction of the fine chrome recovery project is progressing to schedule.
Commissioning of the new expanded fine chrome recovery circuit remains on track 
for Q4 2018. The fine chrome project is expected to significantly enhance revenues
and earnings for the DCM Project. The DCM fine chrome recovery plant targets the
recovery of chrome currently lost by the chrome industry in general. This new fine
chrome recovery plant also serves as a demonstration plant to the chrome industry.
Jubilee has received several enquiries from the chrome industry to also access the
fine chrome currently lost by the industry.

Production rates at DCM have been reduced to facilitate the construction and tie-
in of the new fine chrome recovery plant. The reduced throughput rates will continue
during the construction and commissioning of the fine chrome plant.

The table below presents the operational quarterly performance of the DCM Project:

  |

Chromite concentrate produced

tonnes

  |

Project revenue (GBP’000)^(1)

  |

Project revenue  (ZAR’000)

  |

Project earnings^(2)(GBP’000)

  |

Project earnings (ZAR’000)

  |

Jubilee attributable earnings (GBP’000)

  |

Jubilee attributable earnings (ZAR’000)

  |  
 |

Total Q1 2018

  |

 9 810

  |

 1,240

  |

 20,628

  |

 245

  |

 4,080

  |

 123

  |

 2,040

  |  
 |

Total Q2 2018

  |

9 461

  |

1,066

  |

18,297

  |

74

  |

1,264

  |

37

  |

632

  |  
 |

Total Q3 2018

  |

 8 053

  |

 592

  |

 10,824

  |

(288)

  |

(5,278)

  |

(144)

  |

(2,639)

  |  
 |

Project to date^(3)

  |

 147 973

  |

 15,833

  |

 274,211

  |

 7,572

  |

 130,392

  |

 2,674

  |

 46,554

  |

 

1 = Average monthly conversion rates used

2 = Project earnings include project expenditure on plant and equipment

3= Since April 2017

**PlatCro Project – Platinum (South Africa)**

The PlatCro Project remains on track for commissioning in February 2019. The construction
of the material reclamation and dewatering plant is progressing to schedule which
is targeted for completion during Q4 2018. This plant will facilitate the ramp-up
of material delivery to the Eland platinum concentrator targeting a rate 50 000 
to 60 000 tonnes of platinum rich material per month.

**Kabwe Project – Zinc, Lead and Vanadium Project (Zambia)**

As announced on 6 August 2018, Jubilee was able to ensure that the success of the
Kabwe Project remains independent of the financial position of BMR with the option
to acquire 100% of the Kabwe Project.

Following a detailed technical and engineering review by Jubilee of the Kabwe Project,
its process development teams were able to determine a more suitable process solution
for the recovery of lead and zinc in the surface material than the originally contemplated
acid and brine solution. The enhanced solution includes a dedicated zinc and lead
recovery circuit, initially targeting the recovery of zinc with the discard of the
zinc circuit being further processed in the lead recovery circuit.

A phased execution methodology has been developed which targets an initial processing
rate of approximately 10 800 tonnes per month ramping up to 25 000 tonnes per month
over two further phases. The phased implementation of the process solution links
in with the completion of the pre-processing of the surface material prior to the
zinc recovery plant as well as the implementation of the lead recovery circuit on
the back end of the zinc circuit.

Pilot runs have indicated that we are able to increase the zinc grade through pre-
processing of the surface material by more than 50% prior to introducing the material
to the zinc leach circuit. This upgrading of the feed material successfully buffers
the project’s economic viability against largely fluctuating acid prices in Zambia.
The tried and tested techniques used to achieve the significant upgrade in feed 
material was developed by Jubilee initially for its chrome and PGM operations.

As part of the current strategy Jubilee Metal is reviewing the potential of accessing
existing zinc refining capacity located near the Kabwe Project. The relatively limited
upgrade required to the refinery would offer the potential to significantly shorten
the project execution time line for the zinc recovery circuit. Jubilee has estimated
an upgrade period of approximately 4 months to adapt the refinery to the Kabwe material.
During the interim period while this potential is being assessed, the implementation
of the tailings re-mining facility and the pre-processing plant for the feed material
will continue at the Kabwe Project. Jubilee expects to conclude this strategy review
during Q4 2018.

Share on: