# Jubilee Metals Group Executes Kabwe Project Agreements

- Link: https://www.directorstalkinterviews.com/jubilee-metals-group-executes-kabwe-project-agreements/412750438
- Published: 2018-05-02T07:26:08+01:00
- Author: Giles Arbor

**[Jubilee Metals Group](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l)
Plc** ([LON:JLP](https://www.directorstalkinterviews.com/company/jubilee-metals-group-plc/jlp.l))
has today announced the execution of both a Shareholders’ Agreement and Operating
Agreement with BMR Group PLC to jointly pursue the Kabwe Surface zinc, lead and 
vanadium project in Zambia. The two agreements follow the binding term sheet executed
between the companies as announced on 23 October 2017.

**Highlights**

· Jubilee executes Shareholders’ and Operating agreement with BMR Group PLC for 
the Kabwe surface project

· Jubilee appointed as operator of the Kabwe surface project tasked with concluding
the business plan and implementation of the project

· Jubilee to provide further loan funding of £2,000,000 for an effective 40% ownership
of the joint venture company holding the Kabwe project in addition to holding 29,01%
of BMR Group PLC

> **Leon Coetzer, Jubilee Metals Group Plc Chief Executive commented:** “I am delighted
> to have successfully executed the agreements which capture Jubilee’s participation
> in this very exciting surface processing project.
> Our immediate next project deliverable is to present the project business plan
> to the newly formed joint venture company for approval by the board. I will be
> presenting the project execution plan to the Zambian authorities for approval 
> in the coming days as part of our ongoing engagement with the Zambian mining department.
> Our agreement with BMR calls for the final business and execution plan to be approved
> by the 15th of June 2018. We will continue with site preparation work and confirming
> equipment specifications during this time.
> The Jubilee team is ready to commence with the execution of the project on behalf
> of BMR.”

**Shareholders’ Agreement Overview**

Under the Shareholders’ Agreement, a joint venture company will be established which
will be assigned all intellectual property developed for the execution of the Project
as well as the right to fund and execute the Project on behalf of BMR.

Kabwe Operations is appointed the project manager with Jubilee appointed as the 
operator of the Project, with responsibility for the developing the Project business
plan, joint funding, construction, commissioning and operations of the Project.

In terms of the Shareholders’ Agreement, Jubilee is offered the right to earn into
Kabwe Operations through staged debt funding (“Debt Finance”) as set out below. 
Jubilee’s earn-in interest in Kabwe Operations will be through preferred shares 
issued in Kabwe Operations (“Preferred Shares”), which will have equal voting rights
to the issued ordinary shares of Kabwe Operations and will have the preferred right
to receive 100% of distributed profits from Kabwe Operations until the preferred
Debt Finance plus a 30% interest component is fully paid, where after the Preferred
Shares will convert into ordinary shares of Kabwe Operations.

**Jubilee Key Earn-in Terms for Kabwe Operations:**

(a) Phase 1 – Jubilee has already provided access to funding for Kabwe Operations
to the value of £300,000 to secure a 15% equity interest in Kabwe Operations held
as a Preferred Share.

(b) Phase 2 – Jubilee will provide access to a further £1,000,000 funding towards
the implementation of the approved business plan to secure a further 15% equity 
interest in Kabwe Operations taking the aggregate interest of Jubilee to 30% held
as a Preferred Share. As security for the Jubilee Debt Finance, the BMR Group would
grant security over the whole of its shareholding in the Kabwe project through its
subsidiary Enviro Processing Limited (“EPL”).

(c) Phase 3 – Jubilee will provide access to a further £1,000,000 funding towards
the implementation of the approved business plan to secure a further 10% equity 
interest in Kabwe Operations taking the aggregate interest of Jubilee to 40% held
as a Preferred Share.

**Shareholders’ Agreement – Further Funding Terms**

The amount of any subsequent loan funding required from time to time for the Project
shall be approved by the board of Kabwe Operations in accordance with the Business
Plan presented by Jubilee, and shall be procured by way of:

(a) firstly, loans from shareholders pro rata to their interest in the Kabwe Operations
should the shareholders indicate a willingness to further fund Kabwe Operations 
on terms and conditions to be agreed upon at that time; or

(b) secondly, loans from a financial institution or other third party, upon the 
most favourable terms available; or

(c) thirdly, in the event that funding is unsuccessful as contemplated above, additional
or other loans from shareholders, pro rata to their shareholding.

In the event that any shareholder fails, for any reason to pay all or any of its
pro rata portion of such loan funding, the remaining shareholders shall be entitled
to provide the shortfall in which event the failing shareholder shall be diluted
accordingly.

**Operating Agreement Overview**

(a) Under the agreement, EPL, holder of the Project, appoints the Kabwe Operations
as the managing consultant of the Project and appoints Jubilee as the operator of
the Project to manage, operate and administer the Project for and on behalf of Kabwe
Operations.

(b) Jubilee as operator shall project manage the development and funding of the 
Project, including executing the development work programme and Business Plan of
Kabwe Operations. Jubilee shall in addition submit designs, construct and operate
the plant and shall process the feed material, including the tailings, at the plant
in order to produce and sell into the market saleable product for profit, at the
direction of Kabwe Operations.

(c) As a result of delays caused by the temporary termination of BMR’s Kabwe mining
licence, announced on 7 February 2018 and which was re-instated as announced on 
5 April 2018, Jubilee will prepare the initial design, work programme and budget
for the construction phase of the Kabwe project by 14 June 2018 at which point it
will make a decision whether to proceed with the plant development. In the intervening
period Jubilee, as operator, will also hold discussions with the Zambian authorities
regarding the proposed timing of construction and commissioning of the plant in 
light of the conditions attached to the mining licence at the time of it being reinstated.

(d) BMR and/or EPL have ceded, assigned and transferred to Kabwe Operations the 
IP in relation to the processing methodology for the Project (which is licensed 
to EPL to enable its execution of the Kabwe project in accordance with the specifications
and delivery plans of Kabwe Operations).

Share on: