# Ilika reports on-track progress across Stereax and Goliath in H1 2025/26

- Link: https://www.directorstalkinterviews.com/ilika-reports-on-track-progress-across-stereax-and-goliath-in-h1-202526/4121235998
- Published: 2026-01-22T07:06:36+00:00
- Author: Amilia Stone

**[Ilika plc](https://www.directorstalkinterviews.com/company/ilika-plc/ika.l)**(
[LON:IKA](https://www.directorstalkinterviews.com/company/ilika-plc/ika.l)), a pioneer
in solid-state battery technology, has announced its unaudited half-year report 
for the six months ended 31 October 2025.

**Significant Milestones Achieved on Schedule**

During the period, significant commercial milestones have been met with both Ilika’s
thin-film Stereax miniature solid-state batteries (SSBs) for powering medical devices
and industrial wireless sensors in specialist environments, and its large-format
Goliath cells for electric vehicles (EVs) and cordless appliances.

> **Graeme Purdy, CEO of Ilika, said:**
> _“Ilika has delivered its key targets across both the Stereax and Goliath businesses
> in the period. Having completed the process qualification of our equipment at 
> Cirtec Medical’s facility in the USA, we were able to commence production of the
> initial batches of Stereax prototype product that we released to customers at 
> the end of 2025. This marks a significant step towards full commercial production._
> _“The period started with confirmation that a customer had validated our 2Ah Goliath
> battery prototypes and judged them to be in the leading cohort of SSBs. We built
> on that foundation through collaboration with the UK Battery Industrialisation
> Centre, demonstrating that our process has a clear route to gigafactory manufacturing.
> Upon completion of our automated pilot line in October, we were able to produce
> and ship our first 10Ah Goliath prototypes. Grant funding from the UK Government’s
> DRIVE35 programme managed by the Advanced Propulsion Centre has been important
> in supporting our progress this year. While further funding is expected from grant
> applications which we have in flight, this is not likely to be contiguous with
> our current funding, due to the timing of application and award processes. The
> current DRIVE35 grant is expected to have been fully deployed in Q1CY26 and we
> are confident of further support for our roadmap. All in all, we are pleased with
> progress to date but there is a lot more to do and to come in the second half.”_

**Operational Highlights**

**_Stereax (Medical Device Applications)_**

·    **Completed the manufacturing process qualification** for Stereax batteries
at Cirtec Medical’s facility in Lowell, MA, US; cathode manufacturing initially 
remaining at Ilika’s UK facility as a sub-contracted service to Cirtec.

·    **Commenced production** of Stereax batteries for product testing and initial
deliveries.

·    **Continuing to liaise with our portfolio of 21 customers** including advising
on power management integration into their applications, leveraging Cirtec’s platform
technology portfolio.

**_Goliath (EV Applications)_**

·    **Received customer validation** of 1^(st) generation P1 prototype batteries
confirming they, “_perform to specification, putting them in the cohort of leading
solid-state batteries_“.

·    **Secured further £1.25m grant funding** from the UK Government’s DRIVE35 programme
to produce Goliath A-Samples on industrial equipment, working with the UK Battery
Industrialisation Centre with steering support from JaguarLandRover and the University
of Oxford.

·    **Completed commissioning** of Ilika’s 1.5 MWh/a pilot line, enabling delivery
of larger batteries to customers for evaluation.

·    **Expansion of pipeline** of evaluation agreements by 29%, from 21 to 27 companies,
including EV original equipment manufacturers (OEMs) and Tier 1 suppliers globally,
as well as an increasing number of consumer appliance and defence companies.

**Financial Summary**

·    Total revenue for the period of £0.6m (H1 2024/25: £1.0m), reflecting grant
funding of £0.6m (H1 2024/5: £0.9m) from the commencement of the PRIMED grant project
in the current year against the completion of both HISTORY and SiSTEM grants which
were active in 2024/5.

·    EBITDA loss, excluding share-based payments, of £3.2m (H1 2024/25: £1.9m loss).

·    Successful £4.2 million (gross) fundraising to support the Goliath roadmap 
and Stereax commercialisation.

·    Cash & Cash equivalents at period end of £6.9m (H1 2024/25: £10.1m).

**Post Period End**

·    **Initiated delivery of** prototype M300 Stereax samples to customers meeting
an important commercial milestone.

·    **Shipped** prototype 10Ah Goliath cells to customers for evaluation, a 5x 
increase in capacity relative to the P1 prototypes which were released to customers
in summer 2024. These batteries are estimated to save £2,500 per EV and reduce battery
weight by 20%.

·    **Secured** its first revenue-generating purchase order from Cirtec Medical
for the supply of Stereax electrodes.

**Outlook**

·    We are confident we can **secure larger follow on orders** for the Steareax
M300 batteries from a number of the 21 customers who are currently evaluating the
product for their applications.

·    **Obtain customer feedback** on performance of Goliath 10Ah prototypes and 
refine design to move rapidly towards a minimum viable product A-Sample in 2026.

·    **Broaden Goliath customer base** by further engaging with customers with consumer
appliance and defence applications.

·    Further develop interest in Goliath from our portfolio of automotive and consumer
appliance original equipment manufacturers (OEMs) and Tier 1 suppliers globally,
from our pipeline of evaluation agreements with 27 companies.

**_Analyst Briefing_**

The management team will be hosting a hybrid analyst briefing at 9.30am this morning.
For futher details analysts should contact: FTI Consulting at ilika@fticonsulting.
com. 

Share on: