# Goldplat Plc Expanding with the commission of the processing plant

- Link: https://www.directorstalkinterviews.com/goldplat-plc-expanding-commission-processing-plant/412723142
- Published: 2017-02-06T07:22:05+00:00
- Author: Giles Arbor

**Goldplat Plc** ([LON:GDP](https://www.directorstalkinterviews.com/company/goldplat-plc/gdp.l)),
the AIM quoted African gold producer, is pleased to announce the successful commissioning
of the first stage of the new processing plant at Kilimapesa Gold Limited in Kenya.

The plant has a designed capacity of 200 tonnes per day and will consist of a crusher
circuit; mills; a thickener; leach tanks; an elution plant as well as a tailings
deposition facility. The project has been split into three discreet stages:

 ◦ Stage One: commissioning of the plant excluding the crusher circuit, which is
   now completed
 ◦ Stage Two: installation of the crusher circuit and three additional leach tanks
 ◦ Stage Three: installation of a second mill and a further three additional leach
   tanks.

The decision was taken during 2016 to install a new processing plant and tailings
deposition facility, at a site in close proximity to the Kilimapesa Hill underground
mine, to increase production volume and gold production, decrease operating costs,
optimise overhead costs and to return Kilimapesa to profitability. Due to prevailing
capital market conditions at the time, the Company decided to fund the project internally,
through inter-company loans primarily from the recovery operations. It was also 
decided to construct the plant using existing equipment, and management and skills
from within the Goldplat plc Group where possible. Accordingly, a processing plant
at the Company’s recovery operations in Ghana was deconstructed, containerised, 
and shipped to Kenya. To provide for two production mills and a spare at the new
plant, two additional second-hand mills were also acquired in South Africa. All 
engineering, manufacturing, construction and installation was completed by in-house
teams, with the exception of a few critical work streams, including the overall 
plant layout and design work, and tailings dam design, which were undertaken by 
outside consultants.

Stage One commissioning began on 23 December 2016 and has progressed on time and
on budget. During the latter months of 2016, a stockpile of 6,000 tonnes of crushed
ore was created, which is sufficient to feed/supply the plant until the crusher 
circuit and additional leaching capacity is commissioned.  A key cut for the tailings
facility has been constructed and tailings are currently being deposited into a 
borrow pit contained within the final tailings dam footprint. Plans are underway
to increase the size of the final tailings facility in the near term to further 
reduce costs.

Management is pleased to report, as of the end of January 2017, that production 
is at the planned Stage One rate of 60 tonnes per day, which if maintained, and 
together with ongoing production from the existing plant, equates to an annualised
4,600 ounces of gold production, compared to the 2,005 ounces of gold produced during
the 2016 financial year. At this production rate the mine should be profitable and
in a position to begin repaying loans.

Stage Two installation of the crusher circuit and an additional three leach tanks
has begun and commissioning is expected during April 2017. At this stage the new
plant is expected to process 120 tonnes per day and once the plant is fully commissioned
and producing at steady state, an annualised rate of roughly 4,500 ounces of gold
is planned.  The old plant will continue to produce roughly 2,300 ounces of gold
per year as long as tailings capacity exists, resulting in a potential total production
rate of 6,800 ounces of gold per year.

Stage Three will be planned and commenced based on the performance of the operation
once steady state is achieved.

The new processing plant is scheduled to be opened by the Kenyan Cabinet Secretary
for Mining, Honourable Dan Kazungu, during an official opening ceremony on site 
planned for 16 February 2017.

> **Gerard Kisbey-Green, CEO of Goldplat Plc commented,** “I am very pleased with
> the Board’s decision to proceed with an expansion plan at our Kilimapesa gold 
> mine, which represents an investment of the order of US$2million. Although it 
> is modest in terms of production, we believe it will result in the commencement
> of sustainable profitability at Kilimapesa.  Having achieved a production rate
> of 60 tonnes per day, following the successful implementation of Stage One, I 
> believe we have already proven that we made the right decision.  The team on the
> ground has done a sterling job in adhering to schedules and to budget and we look
> forward to progressing to final commissioning in due course.  Profitability at
> Kilimapesa has been a long time coming and I would like to thank our shareholders
> for their patience in this regard!”

Share on:
