# Fresnillo reports a solid quarter of production, in line with expectations

- Link: https://www.directorstalkinterviews.com/fresnillo-reports-a-solid-quarter-of-production-in-line-with-expectations/4121074754
- Published: 2022-07-27T07:37:31+01:00
- Author: Amilia Stone

**Fresnillo plc **(LON:FRES) has announced its second quarter production report 
for the three months ended 30 June 2022.

> **Octavio Alvídrez, Chief Executive Officer, said:**
> “I am pleased to report a solid quarter of production, in line with our expectations.
> We are making good operational progress, despite the ongoing impact of the pandemic
> and global supply chain bottlenecks, which are likely to persist in the second
> half. We continue to address the challenges presented by the Mexico labour reform
> which limits the use of contractors. Our recruitment and training campaigns are
> proving effective and we should complete this process by year end in our underground
> mines, while our open pit mines are now fully staffed. We expect to achieve the
> tie-in of the Juanicipio plant, our next major growth project, to the national
> electricity grid over the coming weeks and to start commissioning and ramp-up 
> of operations soon after. We remain on track to meet our full year guidance.”

**TOTAL PRODUCTION**

**HIGHLIGHTS**

**Silver**

•    Quarterly attributable silver production of 14.4 moz (including Silverstream),
up 8.1% vs. 1Q22 driven by a higher volume of ore processed and higher ore grades
at Fresnillo and Saucito and a higher ore grade at San Julián Disseminated Ore Body(
DOB).

•    Quarterly attributable silver production (including Silverstream) decreased
3.6% vs. 2Q21 due to the expected lower ore grade and decreased volume of ore processed
at San Julián DOB. This was mitigated by the increased contribution of ore from 
Juanicipio.

•    First half attributable silver production of 27.6 moz (including Silverstream),
in line with 1H21 as the expected lower ore grade at San Julián DOB and lower volume
of ore processed at Saucito was offset by the increased contribution of ore from
Juanicipio.

**Gold**

•     Quarterly attributable gold production of 159.0 koz, up 6.1% vs. 1Q22, primarily
due to the expected higher volume of ore processed at Herradura and Noche Buena.

•     Quarterly attributable gold production decreased 20.6% vs. 2Q21 mainly due
to a lower recovery rate and the expected decrease in the volume of ore processed
at Herradura.

•     First half attributable gold production of 308.8 koz, down 27.9% vs. 1H21 
primarily due to a decrease in the volume of ore processed and lower ore grade at
Herradura and Saucito.  

**Silver Equivalent Basis**

Attributable quarterly silver equivalent ounces of 27.1 moz in 2Q22 (2Q21: 30.9 
moz) and attributable first half silver equivalent ounces of 52.3 moz (1H21: 61.8
moz).

**OPERATING ENVIRONMENT**

The labour reform in Mexico which restricts subcontracting of labour came into effect
from 1st September 2021 resulting in the requirement to internalise a high proportion
of our contractor workforce. The actions we announced to address this short term
challenge, including recruitment campaigns, training and investment in new equipment,
are on-going. We expect to complete the staffing process in the Fresnillo District,
San Julián and Ciénega by year end, and as previously reported, our open pit mines
are now fully staffed. The challenges set out in the first quarter, including a 
tight labour market, global supply chain bottlenecks and cost inflation remain and
these will have some impact in the second half of the year.

**COVID-19 UPDATE**

As reported during the previous quarter, we saw a drop in Covid-related absenteeism
across our operations from March onwards and have seen a more limited impact on 
our operations during 2Q22. Though we have implemented strict protocols to limit
the spread of the virus, a fifth wave has now reached Mexico and we are seeing a
rise in positive cases in the country. Should this trend continue, we will see an
increase in Covid-related absenteeism in the second half. The safety and well-being
of our people is our priority, and we continue to closely monitor the spread of 
the virus and implement a range of safety measures across our business.

**By-Products**

•     Quarterly attributable by-product lead and zinc production increased 18.7%
and 13.0% vs. 1Q22 respectively, driven primarily by higher volumes of ore processed
and ore grades at Saucito and Fresnillo and higher ore grades at San Julián DOB.

•     Quarterly attributable by-product lead and zinc production decreased 11.3%
and 3.2% vs. 2Q21 respectively, due to lower volumes of ore processed and lower 
ore grades at Saucito and San Julián DOB.

•   Similarly, first half attributable by-product lead and zinc production decreased
15.6% and 5.7% vs. 1H21 respectively, primarily due to lower volumes of ore processed
and ore grades at Saucito and a decrease in ore grades at San Julián DOB.

|  | **2Q22** | **1Q22** | **% Change** | **2Q21** | **% Change** | **1H22** | **1H21** | **% Change** | 
| Silver (koz) | 13,664 | 12,528 | 9.1 | 14,092 | (3.0) | 26,192 | 25,931 | 1.0 | 
| Silverstream (koz) | 692 | 748 | (7.5) | 803 | (13.8) | 1,440 | 1,599 | (9.9) | 
| Total Silver (koz) | 14,356 | 13,276 | 8.1 | 14,895 | (3.6) | 27,632 | 27,530 | 0.4 | 
| Gold (oz) | 158,960 | 149,792 | 6.1 | 200,163 | (20.6) | 308,752 | 428,356 | (27.9) | 
| Lead (t) | 14,535 | 12,244 | 18.7 | 16,386 | (11.3) | 26,779 | 31,726 | (15.6) | 
| Zinc (t) | 26,808 | 23,726 | 13.0 | 27,687 | (3.2) | 50,533 | 53,568 | (5.7) |

**DEVELOPMENT PROJECTS**

We expect to complete the tie-in of the Juanicipio plant and Pyrites Plant at Fresnillo
to the national electricity grid in the coming weeks. Commissioning of the Juanicipio
plant will follow soon after with the ramp up of the plant beginning towards the
end of the third quarter.

**SAFETY PERFORMANCE**

The safety and wellbeing of our people remains our absolute priority and we continue
to nurture a strong safety culture across all our mines through the reinforcement
of our safety training and the monitoring of the adherence to our safety policies.
The ‘I Care, We Care’ programme continues to be rolled out across the business and
is a central aspect of all operations and new development projects.

**2022 OUTLOOK**

We remain on track to meet our 2022 full year guidance of 50.5 to 56.5 moz of attributable
silver (including Silverstream) and 600 to 650 koz of attributable gold production.

**INTERIM RESULTS**

Fresnillo will announce its 2022 Interim Results on 2^(nd) of August 2022.