# Firering Strategic Minerals rapidly advancing lime plant modifications

- Link: https://www.directorstalkinterviews.com/firering-strategic-minerals-rapidly-advancing-lime-plant-modifications/4121169512
- Published: 2024-08-28T07:15:41+01:00
- Author: Amilia Stone

**[Firering Strategic Minerals plc](https://www.directorstalkinterviews.com/company/firering-strategic-minerals-plc/frg.l)**(
LON:FRG), an emerging quicklime production and critical mineral exploration company,
has announced an operational update with regards to its quicklime project in Zambia,
which is being refurbished with the goal of commencing phased production during 
Q4 this year.

**HIGHLIGHTS**

_Engineering work at quicklime plant advancing:_

·    New kiln feed conveyor belt installed and commissioned.

·    New brakes installed at skip hoist motor.

·    Rebricking of damaged areas and repairing damaged bridges inside Kiln 1 completed.

·    Widening of the discharge end of Kiln 1 completed.

·    Foundation work for the first gasifier almost complete.

·    Excavation work for coal storage facility commenced.

·    First of two gasifiers on its way to Limeco; each gasifier supports 4 kilns.

·    Several dry runs completed successfully.

_Crushing plant modifications fully operational:_

·    Double roll crusher replaced with impact crusher.

·    Flow sheet partially optimised for efficient production of kiln feedstock in
the right size fraction.

·    Crushing of the correct quality limestone commenced to build a kiln feed pile
ahead of firing Kiln 1 in Q4 of 2024.

·    Waste stockpile renamed ‘secondary stockpile’ due to finding large quantities
of good material suitable for kiln feed.

_On-site laboratory operational:_

·    All new laboratory equipment arrived on site and installed.

·    Testwork focusing on calcium carbonate (“CaCO_(3)“) and quicklime (“CaO”) content
with high purity levels achieved.

·    Purity level specifications are required as part of ongoing discussions with
off-takers.

> **Yuval Cohen, Chief Executive of Firering Strategic Minerals and Limeco, said**:“
> _I am very pleased with the progress being made at Limeco where engineers are 
> rapidly completing the modifications to the lime plant. Key to this plan has been
> the manufacturing of the coal gasifier parts, which are now on their way to Limeco
> having left the Port of Mundra, India, on 23 August 2024. Notably, work on the
> gas ducting required to convey the hot gas from the gasifier to the kilns has 
> also started. _
> _“Having replaced the double roll crusher with an impact crusher, the crushing
> plant is performing well and being used to build a kiln feed pile of the right
> quality limestone with a size fraction of -90mm to 60mm.  Undersize of -60mm is
> guided back to the triple deck screen and split into three different aggregate
> streams for sale to our customers._
> _“Major progress has also been made at Limeco’s onsite laboratory with the arrival
> of all outstanding test equipment. Accordingly, testwork to understand the impact
> of the different limestone qualities and burning times on the production of quicklime
> is in full swing with encouraging initial results showing high available quicklime
> content._
> _“I look forward to further updating the market on the arrival of our first gasifier
> and subsequent installation and commissioning of the system and the firing of 
> our first kiln using this new system during Q4 2024.”_

**DETAILS**

**Lime plant**

A new conveyor belt has been installed (Figure 1) that will feed crushed limestone
to the skip hoist, which transports the materials to a 25t hopper at the top of 
the lime plant. From there, the limestone will be fed first to Kiln 1 and later,
once operational, to Kiln 2.

|  |  |  |  | 
|  | ⌊A large metal structure with pipes Description automatically generated⌉ |  | ⌊A conveyor belt in a factory Description automatically generated⌉ | 
|  |

Figure 1: View of newly installed conveyor belt (left) and feeding arrangement into
skip hoist (right). 

Two new brakes for the skip hoist motor arrived on-site in early August 2024 and
have since been installed (Figure 2), replacing the original single brake. Brake
testwork is planned for September 2024.

![445c764e 3e22 4a1f b848 7a0249fb330a (FRG)](https://dw6uz0omxro53.cloudfront.net/
3152074/445c764e-3e22-4a1f-b848-7a0249fb330a.jpg "Firering Strategic Minerals rapidly
advancing lime plant modifications (FRG)")

Figure 2: View of newly installed brakes for the skip hoist motor.

Repair work inside Kiln 1 has been completed including the repair of cracks, burner
port, the bridge and arches underneath the bridge. Additionally, foundation work
for the first gasifier is advancing (Figure 3) with the last rebar reinforcement
being installed and final concrete of 1050mm poured by the first week of September
2024.

⌊A construction site with workers Description automatically generated⌉⌊A construction
site with workers Description automatically generated⌉
Figure 3: Preparation work
at gasifier foundation ahead of final concrete pour. 

Excavation work for the coal storage facility that will hold the coal stock that
will be fed to the gasifier has commenced (Figure 4).

![A yellow excavator on a dirt hill Description automatically generated](https://
dw6uz0omxro53.cloudfront.net/3152074/9761dec6-c8d3-44a7-8b6a-7ebaf8046be8.jpg "Firering
Strategic Minerals rapidly advancing lime plant modifications (FRG)")

Figure 4: View of excavation work at coal storage facility.

**Crushing plant**

The new impact crusher arrived at Limeco in May and has been successfully installed(
Figure 5). The primary stockpile feed first goes through the primary crusher before
being processed by the impact crusher. The resulting material is then directed to
a double-deck screen, with -90mm to 60mm fractions conveyed to the kiln feed pile(
Figures 6 and 7), and undersized material (-60mm) sent to a triple-deck screen for
sorting into three aggregate streams for Limeco’s clients.

![A conveyor belt in a quarry Description automatically generated](https://dw6uz0omxro53.
cloudfront.net/3152074/3215fdb4-ed18-4f84-b1e9-d7fe9e87f1a8.jpg "Firering Strategic
Minerals rapidly advancing lime plant modifications (FRG)")

Figure 5: View of the newly installed impact crusher.

![A conveyor belt with rocks on it Description automatically generated](https://
dw6uz0omxro53.cloudfront.net/3152074/0b391769-90ef-4c8e-ab8c-4dabbc3838c5.jpg "Firering
Strategic Minerals rapidly advancing lime plant modifications (FRG)")

Figure 6: Belt feeding the -90mm to 60mm size fraction to the kiln feed pile.

![A couple of men standing on a pile of rocks Description automatically generated](
https://dw6uz0omxro53.cloudfront.net/3152074/c8c0d8d5-bcaf-495f-b584-4a0cac1e8086.
jpg "Firering Strategic Minerals rapidly advancing lime plant modifications (FRG)")

Figure 7: View of the kiln feed stockpile.

The stockpile near the quarry, originally referred to as the waste stockpile, was
opened up for further examination to assess its contents. Observations (Figure 8)
and testwork on samples from this stockpile revealed that a large portion comprises
good quality limestone suitable for kiln feed. As a result, the stockpile has been
renamed ‘secondary’ stockpile with the ‘primary’ stockpile located near the ramp
leading to the jaw crusher.

![A person standing on rocks Description automatically generated](https://dw6uz0omxro53.
cloudfront.net/3152074/85c1135f-0ad6-4ce2-a5c0-54db4f065e13.jpg "Firering Strategic
Minerals rapidly advancing lime plant modifications (FRG)")

Figure 8: View of good quality oversize on the ‘secondary’ stockpile and lime plant.

**Laboratory**

Limeco’s laboratory has received all outstanding equipment required to carry out
testwork and populate a database for its limestone qualities.  Figure 9 shows part
of the laboratory equipment and the new oven that was recently installed.

As part of ongoing discussions with off takers, purity level specifications are 
required. Accordingly, Limeco’s laboratory staff successfully produced the first
10kg of quicklime, part of which will be sent to an external accredited laboratory
for independent analysis (Figure 10).** **

|  |  |  |  | 
|  | ⌊A table with different types of objects on it Description automatically generated⌉ |  | ⌊A machine with a red light Description automatically generated⌉ |

Figure 9: View of some of the lab equipment (left) and new oven (right).

|  | 
|  | ⌊A group of men holding bags in a room Description automatically generated⌉ |

Figure 10: Laboratory staff showing the first 10kg of quicklime produced at the 
lab.

**Issue of Equity**

Application will be made to the London Stock Exchange for the admission of a total
of 454,545 ordinary shares of €0.001 each issued to an adviser at an issue price
of 3.3 pence in settlement of fees for services provided of £15,000. It is expected
that Admission will become effective on or around 4 September 2024. Following Admission,
the Company’s issued share capital will consist of 184,246,077 Ordinary Shares which
may be used by shareholders as the denominator for the calculations by which to 
determine if they are required to notify their interest in, or a change to their
interest in, Firering Strategic Minerals under the FCA’s Disclosure Guidance and
Transparency Rules.