# Firering secures Zambian offtake deal as Limeco nears breakeven

- Link: https://www.directorstalkinterviews.com/firering-secures-zambian-offtake-deal-as-limeco-nears-breakeven/4121249372
- Published: 2026-04-20T07:08:01+01:00
- Author: Amilia Stone

**[Firering Strategic Minerals plc](https://www.directorstalkinterviews.com/company/firering-strategic-minerals-plc/frg.l)**(
LON:FRG), a producer of lime products and explorer of critical minerals, has provided
a commercial and operational update on Limeco Resources Limited, its producing lime
products operation in Zambia.

**OVERVIEW**

·    Two-year offtake contract awarded with one of the largest copper producers 
in Zambia, formalising an initial commercial relationship with a significant industry
participant

·    Commercial pipeline expanding, with further prospective clients, including 
leading mining, food processing and manufacturing companies, at various stages of
discussion

·    Effectively breakeven in March 2026, a key milestone in the ramp-up of production
and operational efficiency

·    Kiln 2 discharging at close to target capacity and outperforming Kiln 1 for
the first time since startup; commissioning of Kilns 3 and 4 on track for Q3 and
Q4 2026 respectively, materially expanding production capacity

·    Kiln 1 taken temporarily offline to replicate the successful Kiln 2 modifications,
with sufficient stock held in the silo to meet current demand – optimal timing to
complete the work ahead of rising order volumes

·    Dewatering of the open pit commenced

·    Product mix shifting towards higher-value hydrated lime (commanding a 20-30%
premium to quicklime) and high-purity calcium carbonate (>95% CaCO₃), with the latter
targeting commissioning in Q3 2026 as a new earnings stream

> **Youval Rasin, Chairman and Interim CEO of Firering Strategic Minerals, commented:**_“
> This is an important moment for Limeco. Formalising a two-year offtake contract
> with a major international copper producer – a customer we have been supplying
> for several months – validates Limeco’s product quality and position as a reliable
> supplier to the Zambian mining industry. Reaching effectively breakeven in March,
> alongside a rapidly expanding commercial pipeline and the successful modifications
> to Kiln 2, gives us real confidence in the trajectory of the business. We are 
> using the current period of adequate stock cover to apply the same modifications
> to Kiln 1, a proactive decision that positions us to meet growing demand as Kilns
> 3 and 4 come online later this year. With multiple growth levers in motion, Limeco
> is well placed to deliver a step-change in output and earnings in the near term.”_

**DETAILS**

**Sales**

On 10^(th) April 2026, Limeco was awarded a two-year offtake contract with a major
international mining company to provide a minimum of 1,350 tonnes of hydrated lime
annually for use at its Zambian mining operation. In April alone, Limeco has already
supplied approximately one third of the annual contracted volume, and current run-
rates indicate that actual annualised offtake is expected to exceed the contracted
minimum by a significant margin.

This offtake contract represents an important first step in formalising an established
commercial relationship with a significant industry participant and, as production
capacity increases, Limeco expects to broaden this relationship over time. Importantly,
hydrated lime commands a 20-30% premium to quicklime, and the ongoing shift in product
mix towards hydrated lime is expected to be accretive to margins as volumes scale.
Demand for this product continues to grow across the region.

Whilst a number of smaller sales were made to new clients this month, discussions
with other potential clients continue, including leading mining operators, food 
processing groups and industrial manufacturers, supporting a growing commercial 
pipeline and providing multiple opportunities to expand sales as production scales.

**Operations Update**

Limeco remains focused on increasing output, improving product quality consistency
and bringing additional capacity at its vertically integrated lime products operation
in Zambia.

Production of quicklime continues to progress, supported by ongoing optimisation
and ramp-up activities. Kiln 2, currently in the optimisation phase, continues discharging
at rates averaging over 70 tonnes per day, having now surpassed Kiln 1 total discharge
for the first time since startup.

Work to bring Kilns 3 and 4 online is also advancing, with commissioning expected
in Q3 and Q4 2026 respectively, which is expected to drive a significant step-up
in production capacity. Following the strong performance of Kiln 2 post-modification,
Limeco has taken the decision to apply the same modifications to Kiln 1. With sufficient
quicklime stock held in the silo to meet current demand, and Kiln 2 operating close
to its initial target range, this is the optimal window to undertake the work. Given
the growing order book, this opportunity would not be available if deferred.

As part of its product diversification strategy, Limeco’s manual hydrating circuit
now comprises five units, producing approximately eight tonnes of hydrated lime 
per shift. In response to rising demand and the premium pricing available for this
product, Limeco is actively evaluating options to further expand hydrated lime production
capacity.

Limeco also continues to progress the development of a high-purity calcium carbonate
milling circuit (exceeding 95 per cent CaCO₃). This is expected to establish a new
higher-value commercial product stream, with commissioning targeted for Q3 2026,
opening access to end markets including industrial fillers, paints and coatings,
plastics and agriculture.

Limeco has commenced a dewatering programme at the open pit following the exceptionally
wet rainy season. This is expected to take approximately one month and will enable
access for preparatory works ahead of open pit mining later in the year, supporting
Limeco’s move towards fully integrated, vertically controlled feedstock supply.

**Operating Performance**

Limeco’s overall operating performance improved significantly in March 2026, reaching
effectively breakeven levels. Furthermore, the modifications to Kiln 2 are now bearing
fruit with it outperforming Kiln 1 total discharge rates for the month for the first
time since startup. This represents a key milestone driven by improving production
levels and operational efficiencies, and reflects a marked improvement compared 
to prior months. This provides a strong foundation for further operational scaling
and progression towards sustained profitability as Kilns 3 and 4 come online.

**Critical Minerals Portfolio**

In parallel with the continued ramp-up at Limeco, the Company is progressing with
third party interest at its Atex Lithium-Tantalum Project in northern Côte d’Ivoire.
A further update on Atex will be provided in due course.