# Firering reports stronger Limeco output as Kiln 2 exceeds 70 tonnes per day

- Link: https://www.directorstalkinterviews.com/firering-reports-stronger-limeco-output-as-kiln-2-exceeds-70-tonnes-per-day/4121247651
- Published: 2026-04-02T07:16:29+01:00
- Author: Amilia Stone

**[Firering Strategic Minerals plc](https://www.directorstalkinterviews.com/company/firering-strategic-minerals-plc/frg.l)**(
LON:FRG), an emerging producer of high-quality quick- and hydrated lime, is pleased
to provide an operational update from its Limeco project in Zambia.

> **Youval Rasin, Chairman and Interim Chief Executive Officer of Firering Strategic
> Minerals, commented:** _“Kiln 2 discharge is now at over 70 tonnes per day compared
> to an average of over 60 tonnes per day a fortnight ago, reflecting solid operational
> progress and setting a clear benchmark for the remaining kilns as we scale production
> at Limeco.”_

**DETAILS**

Limeco, the Company’s vertically integrated quicklime and hydrated lime operation
in Zambia, continues to advance its production ramp-up and capacity expansion.

Following completion of hot commissioning of Kiln 2 in February 2026 (see RNS dated
9 February 2026), output is expected to ramp up over an approximate three-month 
optimisation period. Accordingly, performance at Kiln 2 continues to strengthen,
with average output now reaching over 70 tonnes per day.

This level of performance reflects ongoing process optimisation, establishes a clear
benchmark for the remaining six kilns, and increases confidence in Limeco’s ability
to bring additional capacity online efficiently while delivering consistent, high-
quality output.