Firering Strategic Minerals is continuing to advance its Limeco quicklime operation
in Zambia, where the commissioning of an eight-kiln processing plant is central 
to its plans to supply the region’s growing industrial and copper sectors.

The plant has a designed production capacity of between 600 and 800 tonnes of quicklime
per day once all eight vertical kilns are operating. The kilns are being brought
into operation in stages, with commissioning followed by adjustments to improve 
consistency, production rates and product quality.

The process involves heating limestone to high temperatures to change its chemical
composition. Limestone is principally calcium carbonate (CaCO3), which releases 
carbon dioxide when heated, leaving calcium oxide (CaO), commonly known as quicklime.

Although the chemistry is straightforward, maintaining consistent production requires
careful control of operating conditions. Temperature, the time limestone spends 
inside the kiln and the characteristics of the feed material all influence the quality
of the finished quicklime.

This makes the commissioning and optimisation stages important as each kiln is brought
into operation. Adjustments to feedstock characteristics and operating parameters
can help improve production consistency and reduce interruptions.

Limeco’s wider operation includes a two-stage limestone crushing circuit with an
installed primary processing capacity of 300 tonnes per hour. The plant also has
an on-site laboratory to assess limestone and quicklime quality against potential
customer specifications.

Quicklime is used across several industrial applications, including copper processing,
construction and fertiliser production. Zambia’s expanding copper industry provides
a potential source of demand, with the region also relying on imported quicklime.

Firering’s progress at Limeco will therefore depend on its ability to bring the 
remaining kiln capacity into operation, establish consistent production and secure
sales to industrial customers.

The next company updates should provide further information on commissioning progress,
production performance and the development of the operation’s commercial position.

_**[Firering Strategic Minerals plc](https://www.directorstalkinterviews.com/company/firering-strategic-minerals-plc/frg.l)**(
LON:FRG) is an emerging quicklime producer and critical minerals explorer, with 
operations in Zambia and West Africa._

Share on: