# Ferro-Alloy Resources best production quarter to date

- Link: https://www.directorstalkinterviews.com/ferro-alloy-resources-best-production-quarter-to-date/4121125830
- Published: 2023-08-21T07:27:31+01:00
- Author: Giles

**[Ferro-Alloy Resources Limited](https://www.directorstalkinterviews.com/company/ferro-alloy-resources/far.l)**(
[LON:FAR](https://www.directorstalkinterviews.com/company/ferro-alloy-resources/far.l)),
the vanadium producer and developer of the large Balasausqandiq vanadium deposit
in Southern Kazakhstan has provided a trading update in respect of recent developments
at the Company’s existing operations.

**Trading Update**

With all factory upgrades complete, the Company is focussed on increasing production
and recovering more value from each tonne treated, as demonstrated by Q2 2023’s 
best production quarter to date (announced 17 July 2023), in terms of both volumes
of concentrate treated and tonnes of metal recovered across all product lines.

As previously announced, the Company had entered into a number of contracts for 
the supply of vanadium-bearing concentrates to the Company’s existing processing
operation. In order for there to be a constant pipeline of concentrate available
to process, the Company is dependent on the suppliers of the concentrates fulfilling
their contractual obligations, including timely delivery and quality of concentrate,
and on the efficient operation of transport routes for delivery to Kazakhstan.  

In the year to date, one of the Company’s major suppliers defaulted on its monthly
supply commitments. Although deliveries from this supplier were still expected, 
albeit with a long-delayed start date, the Company responded by entering into further
contracts with other suppliers, both long term and on a spot basis. The Company 
was previously satisfied that sufficient deliveries were scheduled to enable the
Company to run at full operating capacity from mid-July 2023 onwards. However, further
unanticipated supplier and transport delays have been experienced and have impacted
output across the first two months of Q3 2023.

Concentrate supplies already in transit and ready for shipment are sufficient to
allow the resumption of full operations from around the beginning of September. 
However, there is a possibility of further delays in the Southern, trans-Caspian
Sea transport routes, caused by Ukraine-related disruption to other import routes
and exacerbated by winter conditions in the Caspian Sea. There is, therefore, a 
possibility of some more limited shortfalls affecting production in Q4 2023. Subject
to this, the Company expects the processing and output of the plant for Q4 2023 
to be at or close to planned capacity.

Vanadium prices have remained depressed compared with prices earlier this year, 
attributed to the economic slow-down in China resulting in net exports of vanadium
from China, although this is likely to be offset by significant demand for vanadium
for energy storage batteries.

As a result, the Company anticipates that the concentrate supply delays experienced
in Q3 2023, and continuing low vanadium prices, will have a material impact on the
Company’s financial results for Q3 2023.

**Feasibility study**

The feasibility study into the Balasausqandiq deposit, the main value driver of 
the Company, is ongoing and reaching the final stages.

The previous Competent Person’s Report issued in 2018 showed a combined (Phases 
1 and 2) Net Present Value of US$2 billion. Since then, as previously announced,
the ore resource estimated for the first ore body (OB1) showed an increase of 23%
in contained vanadium compared with the previous estimate and the ongoing investigation
of the possibility to use a concentrate of the carbon content of the ore as carbon
black has produced exciting results. Other results have been in line with previous
expectations.

Ferro-Alloy Resources announced on 27 July 2023 the launch of an exempt offer bond
programme on the Astana International Exchange. So far, a total of US$1.3m has been
raised out of the first US$3m tranche of the programme. The US$1.3m, and all subsequent
funds raised under the first tranche of the programme, will be used to fund the 
ongoing feasibility study to completion.

**Outlook**

The Company believes that both the production and financial results for 2023 are
still likely to be significantly better than those achieved during 2022 notwithstanding
the concentrate supply issues incurred to date.

The main activity for the remainder of 2023 will continue to be the completion of
the Balasausqandiq feasibility study. Current schedules indicate that the study 
will be completed before the end of the year but indications of possible delays 
have been received from our consultants which might extend the delivery of the study
into the first quarter of 2024.

> **Nick Bridgen, Ferro-Alloy Resources** **CEO, commented**: _“With all plant modifications
> now complete and operating efficiently, these supply chain issues are disappointing.
> That said, the progress in the feasibility study, the main driver of the Company’s
> value, is very encouraging and I look forward to updating shareholders on its 
> results.”_