**Edenville Energy plc** (LON:EDL), the company developing a coal project in southwest
Tanzania, has today provided an update on activities in connection with its recently
established commercial coal production and coal to power project.

**Commercial Coal Production**

Since the start of commercial coal production in October 2017, the Company has been
refining all aspects of the operation and selling coal to commercial customers.

**Mining**

Edenville’s mining operations are proceeding as anticipated, with high quality near
surface coal being extracted from the Mkomolo deposit. Mining operations have been
able to keep pace with demand and plant capacity despite the seasonal heavy rains.

To help fulfil the demand for coal we are experiencing and to potentially increase
the amount of unprocessed coal the Company can sell, the Company has taken the decision
to also start mining the Namwele deposit. Namwele, which sits to the south of the
Mkomolo deposit, will be mined by our Tanzanian partner, Upendo Group Ltd (“Upendo”).
Upendo has already started clearing the overburden and we expect the first Namwele
coal to be mined before the end of Q1 2018.

**Coal Quality**

We are very pleased to report that coal quality, in terms of both calorific value
and ash content, is exceeding management’s initial expectations when mining commenced.
Both the raw mined and processed coal has been extensively tested at our on-site
laboratory and has returned values that meet our customer’s requirements.

Recent results from our on-site laboratory have given encouraging calorific values
for Mkomolo, including 6,734 GCV (Gross Calorific Value in Kcal/Kg) on an air-dried
basis, correlating with previous results from December 2017. Additionally, and of
particular note, is the energy value contained in our raw coal fines material (material
generally less than one sixteenth of an inch in size), recently testing at 4,753
GCV on an as received basis.

Should these values continue to be seen, we consider this will not only have a positive
effect in terms of the value of commercial sales, but also on the long-term economics
of the power plant development and related coal supply. This material would not 
require washing, thereby increasing the potential fuel supply for the coal to power
project. Additionally, there may be the potential to sell some of this high calorific
coal without it having to be processed through the wash plant, increasing the amount
of coal the Company can sell.

**Processing plant**

The Company’s wash plant and associated equipment is currently running at a throughput
of 30 to 40 tonnes per hour, operating six days a week for 8 to 10 hours a day. 
Edenville is therefore in a position to process 8,000 to 10,000 tonnes of mined 
material per month.

During the ramp up of operations higher than expected amounts of mudstone and fines
were encountered, which reduced throughput in the processing plant. As a result,
unit processing costs were marginally higher than management expected, however, 
this was offset by lower than expected unit mining costs.

Subsequently the Company intends to install both a Lamella water treatment system
and pre-screen technology to improve the overall efficiency of the plant. The Lamella
water treatment system will remove mudstone and coal fines from the water, providing
the plant with cleaner water and the pre-screen technology will pre-screen the mined
material, removing coal fines before they reach the wash plant. Once implemented,
hourly production rates should increase to 80 to 100 tonnes per hour, thereby bringing
operational costs per tonne back in line with management expectations, in parallel
with the plant reaching its full production capacity.

**Coal orders**

Throughout January we have continued to process and ship the bulk preliminary orders
detailed in the announcements made on 23 November 2017 and 8 January 2018. We remain
in detailed discussions regarding contractual terms with several of these groups
and others regarding potential long-term orders that total over 10,000 tonnes of
coal per month.

Additionally, the Company has received further orders for trial material in the 
last fortnight. These requests include one for 4,000 tonnes of coal from an industrial
customer. This customer has indicated that, if the product is demonstrated to be
appropriate for their needs in trials, they would seek to increase their order.

In aggregate, trial and other orders for approximately 9,000 tonnes of coal have
now been received and these have either been shipped or are in the process of being
fulfilled. All have been, or are being, supplied on a commercial, paid for, basis.

These trial orders have been substantially larger that we initially envisaged and
continue to be received and shipped. Through these we believe we are demonstrating
the quality of our coal and the ability of Edenville to be a trusted and reliable
supplier. The entering into of the long-term coal supply contracts we are currently
discussing crucially depends on the ability to secure reliable and cost-effective
transport for the coal. To that end, we and our customers are in negotiations with
a number of transport providers. Additionally, we are investigating the appropriateness
of having our own base fleet of trucks to ship coal to customers, reducing our dependence
on third party transport providers. At present, no assurances can be given as to
the form that any long-term coal supply contracts may take, but we are confident
that once logistical issues are resolved long term contracts can be entered into
and further updates will be provided as appropriate.

**Coal to Power Project**

The Company continues to work with its partner Sinohydro Corporation of China (“
Sinohydro”) to progress the Company’s coal to power project. Sinohydro’s representatives
have completed their pre-feasibility and economic assessment work and remain very
supportive of the project. Since the last update on 23 November 2017 further productive
meetings have been held with the Tanzanian Ministry for Energy (the “Ministry”) 
and Tanzania Electric Supply Company (“Tanesco”) to progress the project. It should
be noted the opening up of the mine has provided the Company with valuable data 
on the coal quality and structure of the deposit, critical when considering the 
power plant design which will depend on this fuel source.

In line with other coal to power projects in Tanzania, the Company is progressing
discussions with a view to, in the first instance, entering into an MOU with the
Ministry and Tanesco setting out, inter alia, the size of the project, the proposed
structure of a Power Purchase Agreement (PPA), tariff levels, and connectivity into
the planned transmission line that will pass through the Sumbawanga Region. The 
timing of this is largely in government hands, although we continue to have a very
good working relationship with them and they recognise the demonstrable benefits
the Edenville Energy PLC project would bring to the region.