# Edenville Energy PLC Project Construction Update

- Link: https://www.directorstalkinterviews.com/edenville-energy-plc-project-construction-update/412734125
- Published: 2017-08-25T07:18:56+01:00
- Author: Giles Arbor

**Edenville Energy plc (LON:EDL)**, the company developing a coal project in south
west Tanzania, has today provided an update on construction at the Company’s Rukwa
coal project site.

**Key Points**

· Plant components delivered to site and construction commenced

· Screen undergoing operational tests

· Independent assay results returned positive raw coal values of 5,220Kcal / Kg 
and 15.7% Ash

· Several groups expected to take delivery of coal in the coming weeks

· Promotion of coal in East Africa region ongoing with assistance of a Marketing
Agent

The majority of the wash plant components are now on site with the last shipment
due for delivery next week. Construction has commenced with the concrete foundation
pad for the drum section in the finals stages of completion. Emphasis has been placed
on establishing the screen component as rapidly as possible and this is now completed
and undergoing operational testing (see attached photo [insert link here]). This
will allow sized coal to be distributed to customers who have requests pending.

Recent independent assay results carried out on the Mkomolo seam currently being
exposed have returned raw coal values of 5,220Kcal / Kg ( 21.93Mj) and 15.7% Ash.
We are very encouraged by these numbers and consider when this coal is processed
through the wash plant a premium product can be obtained.

Stripping of overburden is exposing significant quantities of coal in readiness 
for the plant. Overburden at this stage is soft and friable which is helping to 
achieve high digging rates.

The completion of the screen will provide a consistently sized product and four 
groups are planning to take delivery of screened product shortly. We are in communication
with others to take both screened coal and washed coal once the plant construction
is completed.

In addition to the Company marketing the coal, we have an agent actively exploring
new client possibilities in the region, including in Kenya, Rwanda and Uganda.

In parallel with the plant a laboratory is being built on site that will be able
to provide proximate analysis data for quality control. This is scheduled to be 
operating at the same time as the plant.

Edenville Energy plc will continue to update the market on the progress of construction
in the coming weeks.