**Edenville Energy plc** (LON: EDL), the company developing a coal project in southwest
Tanzania, has today provided its latest update on developments at the Company’s 
Rukwa Coal Project.

As stated in the announcements made on 6 November 2018, 17 December 2018 and 20 
December 2018 the net proceeds of the US$750,000 Initial Loan from Lind are being
used by the Company for a number of purposes. This includes the purchase of a second
excavator to open up the new mining area to the north of the current excavations.
The Company is pleased to confirm that this second excavator has now been acquired
and together with the existing excavator and four additional hired haul trucks, 
is in operation at the Company’s Project site.

These vehicles are currently all being employed to increase the amount of material
being mined from the existing pit, but the newly acquired second excavator and associated
haul trucks will shortly move to the new northern mining area to begin opening this
up. The mobile in-pit lighting to allow 24 hour per day operation in the existing
pit has been installed, further increasing the Company’s mining capacity.

As stated on 17 December 2018 the land compensation process and required regulatory
documents for the northern mining area were completed and submitted by the Company
to the relevant Tanzanian Government authorities. The Company is pleased to confirm
that the relevant government authorities have now provided their approval and land
compensation payments are being made, together with detailed delineation of the 
northern mining area being undertaken. The Company anticipates that mining of the
new northern area will commence shortly and will provide further updates regarding
progress as soon as practicable.

As announced on 20 December 2018, the Lamella clarifier water treatment plant is
now fully operational and has been delivering the anticipated improvements to both
water qualities in the plant process and in the return ponds, leading to increased
coal processing plant productivity.

Construction of the pre-screening plant and conveyors, designed to remove the majority
of coal fines before they reach the washing circuit, is now complete and the plant
is now undergoing testing. Alongside this testing, further refinements are being
made to the feed hopper. It is expected that the pre-screen plant will be fully 
integrated into the Company’s washed coal production process by the end of January
2019.

Edenville Energy plc management believe that these developments, when complete, 
will increase that amount of washed can that can be produced from the Project and
the Company looks forward to providing further updates as matters progress.

As announced on 11 December 2018, the Company intends to transition its Nominated
Adviser role from Northland Capital Partners Limited to SP Angel Corporate Finance
LLP. This process is progressing and a further announcement will be made as appropriate.