**Edenville Energy plc** (LON:EDL), the company developing a coal project in southwest
Tanzania, has today announced its audited results for the year ended 31 December
2017.

**2017 Highlights**

· Infrastructure purchased and commissioned to allow mining operations to commence
and coal to be processed

· Mining licence enlargement completed

· Commencement of mining at the Company’s Rukwa site

· Trial shipments to commercial customers made

· Further progress on Power Plant Project

**Post Period Highlights**

· Operation of the mine and wash plant developed following the construction phase
and a variety of sized coal products are being produced

· From 1 January 2018 to 24 May 2018 approximate numbers show 20,634 tonnes of Run
of Mine coal processed, producing 5,665 tonnes of washed coal and 9,285 tonnes of
fine coal

· Of the 5,665 tonnes of washed coal, 3,101 tonnes has been shipped and the Company
is in receipt of orders that in aggregate total more than the currently stockpiled
washed coal

> **Commenting, Jeffrey Malaihollo, Chairman of Edenville Energy Plc, said:** “2017
> was a pivotal year for Edenville as we moved from being an exploration company
> through to producing coal. It is a significant achievement to construct and operate
> a modern coal mine within approximately eight months and I believe the Company
> is now well positioned for the future.
> “As we move through 2018 we intend to increase production levels from our Rukwa
> Mine and report further sales and contracts in the coming months, whilst continuing
> to progress our Power Plant Project.”