# Cora Gold moves Sanankoro closer to construction

- Link: https://www.directorstalkinterviews.com/cora-gold-moves-sanankoro-closer-to-construction/4121264412
- Published: 2026-09-29T13:00:00+01:00
- Author: Amilia Stone

[Cora Gold](https://www.directorstalkinterviews.com/company/cora-gold-ltd/cora.l)
has completed key engineering and pre-construction work at its Sanankoro Gold Project
in southern Mali, moving the development closer to construction while it continues
to work towards securing the required mining permit.

The company has completed fieldwork and three-dimensional plant modelling as part
of the front-end engineering design (FEED) programme being carried out by SENET,
a subsidiary of DRA Global. FEED remains on schedule for completion in the fourth
quarter of 2026.

The completed modelling covers the project’s main processing areas, including run-
of-mine operations, crushing and milling, the scrubber and ball mill circuit, and
the carbon-in-leach and elution circuits. Key equipment suppliers are also involved
in the design of the comminution, CIL and elution packages, helping Cora progress
decisions around major equipment requirements.

Cora has also completed land compensation covering 174 hectares required for the
planned tailings storage facility. Geotechnical work has been carried out at the
proposed processing plant and power station sites, with the results expected to 
inform foundation designs.

The exploration camp has also been upgraded ahead of development. Work included 
improvements to security, accommodation and utilities, alongside additional water
storage capacity. These activities are intended to support the transition towards
construction once the necessary approvals are in place.

_**Cora Gold Ltd** (LON:CORA), together with its subsidiaries, explores for and 
develops mineral projects in West Africa. The company primarily explores for gold
deposits. Its flagship project is the Sanankoro Gold project located in the Yanfolila
Gold Belt, Southern Mali._