# Cora Gold moves closer to construction readiness at Sanankoro as funding risk recedes, Cavendish

- Link: https://www.directorstalkinterviews.com/cora-gold-moves-closer-to-construction-readiness-at-sanankoro-as-funding-risk-recedes-cavendish/4121261768
- Published: 2026-09-05T08:10:00+01:00
- Author: Anthony Fox

**[Cora Gold](https://www.directorstalkinterviews.com/company/cora-gold-ltd/cora.l)
Ltd** (LON:CORA) is continuing to advance its flagship Sanankoro gold project in
southern Mali, with Cavendish highlighting progress on funding, permitting, engineering
work and exploration in its latest research note from 4 September 2026.

The broker describes the first half of 2026 as a significant period for the AIM-
listed gold exploration and development company. Most importantly, Cavendish believes
funding risk was effectively removed after Cora completed a £15.7 million equity
fundraise in March, followed by the signing of a US$120 million Gold Stream financing
package in April.

Research Analyst Nick Chalmers wrote: “Cora enjoyed a transformational 1H26, although
the financial results reported today are largely academic.”

The funding arrangements provide Cora with a committed construction financing solution
for Sanankoro, while the company retains flexibility over how that funding is ultimately
structured.

## Cora Gold 1H26 and operational highlights

 * Cora completed a £15.7 million equity fundraise in March 2026.
 * The fundraise was cornerstoned by Eagle Eye Asset Holdings, which became Cora’s
   largest shareholder with a 29.9% interest.
 * Cora subsequently signed a US$120 million Gold Stream financing package with 
   Eagle Eye Asset Holdings in April.
 * The company has additional time to replace up to 50% of the Gold Stream with 
   senior debt.
 * Front-End Engineering & Design, or FEED, work began in May and is expected to
   be completed during the second half of 2026.
 * A 12,000 metre drilling programme commenced in June, targeting extensions to 
   existing deposits and prospective near-mine targets.
 * The first interim renewal of the Sanankoro II exploration permit was announced
   ahead of the latest Cavendish research note.

## Greater flexibility over Sanankoro financing

The period during which Cora can replace 50% of the Gold Stream with senior debt
has been extended to the later of 30 October 2027 or six months after the Sanankoro
mining permit is granted.

Cavendish sees this as giving Cora additional time to optimise the financing structure
while maintaining access to a committed construction funding solution.

Under the current arrangement, Eagle Eye Asset Holdings is entitled to purchase 
30.44% of Sanankoro’s life-of-mine gold production at 20% of the prevailing gold
spot price. That entitlement would fall to 15.22% if Cora replaces 50% of the Stream
with debt.

The research note also says Cora continues to see positive appetite from several
West African-focused banks for traditional senior debt.

## Sanankoro permitting remains a key milestone

Obtaining the Sanankoro mining permit remains central to the project’s development
timetable.

The first interim renewal of the Sanankoro II exploration permit was described by
Cavendish as another step towards consolidating the project’s mining infrastructure
under a single mining permit.

Cora continues to engage with the Malian authorities regarding the remaining renewals,
with the Bokoro II and Kodiou exploration permits identified as the next steps. 
Once those renewals are secured, the company expects to be able to progress its 
application for the mining permit required before construction can begin.

Cavendish has moved its assumed construction start to the first half of 2027 from
the second half of 2026. This change has resulted in the broker reducing its short-
term target price from 27.0p to 25.8p per share.

Even after that adjustment, the new target represents 177% upside to the 9.3p share
price quoted in the research note.

## Engineering work aims to shorten the route to production

Cora is also undertaking work intended to ensure Sanankoro is ready to move towards
construction once the mining permit is received.

FEED work began in May and, according to Cavendish, is progressing well. The process
should allow Cora to make decisions on long lead-time equipment and other items 
before construction begins.

Cavendish expects FEED to be completed during the second half of 2026, while Cora
is also advancing complementary preparatory workstreams.

This work is intended to compress the future delivery timetable and support a quicker
transition towards production once the necessary permitting is in place.

## Sanankoro economics remain a key part of the investment case

Cavendish also points to the economics contained in the updated Sanankoro definitive
feasibility study financial model released in May.

At a gold price of US$4,000 per ounce, the project model indicated an NPV8% of US
$461 million and an internal rate of return of 119%, before adjustment for the Gold
Stream arrangement.

The broker noted that project economics would be stronger at the approximately US
$4,515 per ounce spot gold price referenced in its report.

Cavendish’s valuation work on page four of the note gives Cora a fully diluted sum-
of-the-parts valuation of 25.8p per share. The broker values Sanankoro, resources
outside reserves and the exploration target alongside forecast net cash and other
items.

## Exploration could add further value

Beyond construction preparation, Cora is continuing work designed to expand the 
Sanankoro resource base.

A 12,000 metre drilling programme started in June, targeting extensions of existing
deposits as well as near-mine exploration opportunities. The aim is to identify 
opportunities that could ultimately support higher production, extend mine life,
or both.

Cavendish also believes the shares are undervalued relative to a selection of African
peers. On page five of its report, the broker says it expects Cora’s valuation to
move closer to peer levels as important milestones are achieved, particularly receipt
of the Sanankoro mining permit and continued project de-risking.

## Final Thoughts

Cora Gold enters the next stage of Sanankoro’s development with funding arrangements
in place, FEED progressing and further exploration underway. The mining permit remains
the most important near-term milestone, and Cavendish has pushed its assumed construction
start into the first half of 2027 to reflect the revised timetable. Even after reducing
its target price to 25.8p, the broker continues to see substantial potential relative
to the 9.3p share price used in its research note.