# Centamin plc Sukari Gold Mine 36MW solar farm contract awards

- Link: https://www.directorstalkinterviews.com/centamin-plc-sukari-gold-mine-36mw-solar-farm-contract-awards/412984802
- Published: 2021-05-04T07:30:16+01:00
- Author: Giles

> **Martin Horgan, Centamin plc** **CEO **commented: _“Centamin’s decision to integrate
> sustainable solar power at Sukari is fully aligned with our commitment to responsible
> mining.  It has enabled us to marry up our environmental stewardship philosophy
> with our strategic objective of maximising returns for all stakeholders. With 
> phase one of the project near complete, including completion of the pioneering
> works across the 85-hectare site, concluding these definitive engineering, procurement
> and construction contracts was the next significant milestone in delivering the
> Sukari solar plant.  Working with our partners we will deliver the largest hybrid
> solar project of its kind, which will reduce our fuel consumption and greenhouse
> gas emissions from 2022 onwards.”_

**SOLAR POWERING SUKARI INTO THE FUTURE**

**Centamin plc** (LON:CEY) has announced it has awarded the engineering, procurement
and construction contracts for the 36MW solar farm and 7.5 MW battery-energy storage
system at the Sukari Gold Mine to:

·     juwi AG (“juwi”): juwi has been contracted to design, supply and integrate
the Sukari solar and battery plant into the current diesel power plant. juwi are
renewable energy specialists, with an established track record of developing and
integrating renewable energy solutions for mines; and

·     Giza Systems (“Giza”): Giza have been contracted to install the Sukari solar
plant. Giza are systems integrators in the Middle East and Africa region. Solar 
is a rapidly growing source of power within Egypt and Centamin is able to benefit
from the expanding local expertise, whilst remaining committed to promoting and 
prioritising local socio-economic partnerships.

The Sukari solar plant will be the largest hybrid solar project at an off-grid mining
operation globally and is expected to reduce diesel fuel consumption at Sukari by
an estimated 22 million litres per annum and lower carbon emissions by an estimated
60,000 tonnes CO_(2)-e per annum. The project is scheduled to be commissioned late
in H1 2022.

Sukari is optimally located within Egypt’s Eastern Desert which has some of the 
highest levels of solar irradiance globally, averaging over ten hours of sunshine
a day throughout the year. To maximise the total energy generation, the project 
will use bifacial solar PV modules and a single axis tracking. juwi Hybrid IQ micro-
grid technology will enable the integration of the solar and battery system into
the existing off-grid network and support the operation of the existing power station.

Further benefits of integrating solar as a sustainable power solution are the reduction
in operating costs, including an estimated US$9-13 million savings in annual fuel
costs and reduced exposure to fuel price volatility; increased reliability of the
power system; and reduced traffic and fuel transport to and from site. The project
has been engineered with a longer-term outlook, enabling the solar and battery capacity
to be increased if required.

The total project capital expenditure is estimated at US$37 million.