producer, with ownership of high grade vanadium has today provided a Q2 operational
update for its 84%-owned energy subsidiary, Bushveld Energy Limited.

**Operational Highlights for the second quarter**

Eskom Vanadium Redox Flow Batteries project:

· Bushveld Energy and the Industrial Development Corporation received delivery of
the first vanadium redox flow battery from UniEnergy Technologies in South Africa.
This included the mixed-acid vanadium electrolyte that will be used in the battery;

· The utility scale battery was delivered within months of the order being made;

· Bushveld Energy’s team is performing all the integration work related to the VRFB
at the Eskom Research and Innovation micro-grid site in Roshverville, South Africa;

· All site preparation work has been completed at ERIC;

· Preparation of the VRFB controls for integration to Eskom’s existing site controller
at the facility is complete;

· Two technicians from Bushveld Energy were trained on the installation, operation
and maintenance of the VRFB at UET’s production facility in the USA. The training
will continue during the commissioning process which is expected to conclude in 
July, as UET is sending two engineers to South Africa to oversee the process; and

· Bushveld Energy and Eskom expect to receive initial data on the VRFB’s performance
at the facility during the coming quarter. The analysis of the results will help
to inform the technical and commercial merits of future energy storage projects.

Vanadium electrolyte production facility:

· Bushveld Energy awarded the contract to perform an Environmental Impact Assessment(“
EIA”) to a South African consultancy for the greenfield facility in the East London
Industrial Development Zone (“ELIDZ”);

· Based on recommendations from the consultant, a full EIA will be performed, rather
than a basic assessment as originally envisaged;

· The EIA will cover both the initial 200MWh capacity for the plant and allow for
future production expansion;

· While this will require up to three months for community engagement and other 
processes, the long-term benefit will be the ability to increase capacity without
securing another EIA;

· An EIA is also required for the chemicals plant that will be co-located with Bushveld’s
existing mining and processing facility at the Vametco vanadium mine. This application
will be combined with Vametco’s overall expansion application and thus not add any
additional time or cost to Vametco’s EIA process, highlighting an example of the
synergies of vertical integration in Bushveld’s business model; and

· The project remains on track to produce electrolyte in 2019 for South African 
and international markets.

> **Fortune Mojapelo, CEO of Bushveld Minerals Limited, commented:** “In the second
> quarter, the first ever vanadium redox flow battery was delivered to South Africa.
> As the integrator for the project, Bushveld Energy and its team have been able
> to expand its expertise on project delivery and implementation. This has significantly
> assisted to build our capability to develop and deliver energy storage projects
> across the African continent.
> This project has shown that utility scale batteries can be delivered in only months.
> Simultaneously, we are advancing the component manufacturing aspect of our business,
> where we are building flexibility for quick expansion. This strategy allows us
> to keep initial risk lower with an ability to capitalise should growth in energy
> storage materialise even faster than expected. With these efforts, Bushveld Energy
> is positioning itself in Africa with a unique combination of technical skills 
> and component supply to deliver energy storage solutions.”

**Summary of 2018 Project Objectives**

Share on: