# Bluefield Solar secures Gate 2 grid offers for over 90% of 1.34GW pipeline

- Link: https://www.directorstalkinterviews.com/bluefield-solar-secures-gate-2-grid-offers-for-over-90-of-1-34gw-pipeline/4121236275
- Published: 2026-01-23T07:40:09+00:00
- Author: Amilia Stone

**Bluefield Solar Income Fund Limited **(LON:BSIF), the London listed UK income 
fund focused primarily on acquiring and managing solar energy assets, has confirmed
that following the first stage of National Energy System Operator’s grid reform 
process, the Company received Gate 2, Phase 1 offers on c. 660MW of its development
pipeline.

NESO’s grid reform process is a major overhaul of how energy projects connect to
Britain’s electricity grid, designed to clear a huge backlog, prioritise ‘ready 
to go’ projects, and align the system with the UK’s Clean Power 2030 goals. It replaces
the old first come – first served queue with a readiness and strategic alignment
based system, removes stalled projects, and introduces a new process to accelerate
delivery.

Receipt of a Gate 2, Phase 1 offer means that projects have had their connection
date confirmed as being between 2026-2030 and so have attained a highly protected
status in the queue of projects to be connected to the grid. The technology split
across the Gate 2, Phase 1 offers for the Company’s development pipeline is c. 540MW
solar PV and c.120MW BESS.

Bluefield Solar is also pleased to confirm that it has received Gate 2, Phase 2 
offers on c. 560MW of its development pipeline, split between c. 185MW PV and c.
370MW BESS. Receipt of a Phase 2 offer means projects have been allocated a grid
connection date between 2031-2035.

This means of the Company’s c. 1.34GW pipeline, over 90% has received Gate 2 offers.
The remaining 9% of the pipeline that was allocated Gate 1 offers corresponds to
125MW BESS. Projects allocated Gate 1 offers will need to re-apply for new grid 
offers to re-enter the grid queue, upon which connection dates offered will depend
on application of NESO’s strategic alignment criteria. The Company is also able 
to confirm that projects which have been allocated Gate 1 offers have not been allocated
any value within the Company’s NAV to date.

The success of the grid reform process is testament to the strategy designed and
implemented by the Investment Adviser in 2020 and has resulted in the Company having
a highly valuable pipeline.

**Update on Formal Sale Process**

The Strategic Review and Formal Sale Process announced by the Company on 5 November
2025 continues in line with the Board’s expectations. The Company will provide a
further update when it issues its interim results in early March 2026 unless there
are any material developments in the meantime.