# Avanco Resources Limited Site visit – progress on all fronts

- Link: https://www.directorstalkinterviews.com/avanco-resources-limited-site-visit-progress-fronts/412737343
- Published: 2017-10-03T09:02:35+01:00
- Author: Giles Arbor

A recent visit to **Avanco Resources Limited** (ASX:AVB) projects in northern Brazil
confirmed our belief that the group’s portfolio has significant growth potential,
and that the company has a management team with the technical capability and local
know-how to realise this potential. The Antas mine is on course to produce 13.5-
14.0kt of copper at cash costs of US$1.35-1.50/lb in 2017, which we estimate could
generate group EBIDTA of US$28m. This is enabling Avanco to internally fund reserve
extension drilling at the mine and to progress feasibility study work at its two
key growth projects, Pedra Branca and CentroGold. The former could be in production
by mid-2020 and see Avanco grow group copper output to 40-50kt pa over the longer
term. The latter could be developed as a c100koz pa gold operation by as early as
H2 2019, subject to permitting resolution. With an EV that equates to 5.7x our 2017
EBITDA estimate (and just 4.3x our 2018 estimate), we feel this growth potential
is far from fully reflected in Avanco’s undemanding current market valuation.

**Antas performing well:** Antas continues to build on its strong start to production
last year, and looks well on course to meet management’s 2017 full-year guidance
of 13.5-14.0kt copper and 9.75-10.5koz gold at cash costs of US$1.35-1.50/lb. Our
operational forecasts are unchanged, but we have raised our copper and gold price
estimates for H2 2017 after marking-to-market for recent positive movements – our
2017 EBITDA estimate rises to US$28m accordingly (up from US$26m previously).

**Fuelling progress on projects:** Cash flow is being reinvested in resource/reserve
drilling in a bid to extend Antas’ life of mine – an initial drill programme is 
complete and will feed an updated mine plan later this quarter. It is also funding
resource upgrade drilling and development study work at Pedra Branca and CentroGold.
Avanco has been busy optimising the recent Pedra Branca prefeasibility study and
we expect an update by year end, leading in to full feasibility study completion
in Q2 2018. Subject to permitting and financing, this could see construction commence
during 2019, and first production around mid-2020. As a simpler (and likely cheaper)
open-pit development, CentroGold could well jump ahead of Pedra Branca in the timetable,
subject to legacy permitting issues being resolved. Having recently negotiated an
acceleration to the acquisition of 100% ownership in the project, we anticipate 
increased news flow around CentroGold, including a scoping study this quarter (building
on the substantial body of historical work).

**Valuation:** Avanco Resources Limited is trading at a significant discount to 
our sum-of-the-parts NAV estimate of A$0.18/share (which see scope to increase with
permitting and development study progress at CentroGold). We think this discount
should narrow as copper continues its recovery (we use a conservative long-term 
price assumption of US$3.00/lb from 2019) and as Avanco further optimises production
at Antas and de-risks and ultimately develops Pedra Branca and CentroGold.