# Anglo American Platinum ramps up ACP plant to restart refined PGM production

- Link: https://www.directorstalkinterviews.com/anglo-american-platinum-ramps-up-acp-plant-to-restart-refined-pgm-production/412817994
- Published: 2020-05-05T07:07:50+01:00
- Author: Amilia Stone

**[Anglo American plc](https://www.directorstalkinterviews.com/ftse-company/anglo-american/aal.l)**(
[LON:AAL](https://www.directorstalkinterviews.com/company/anglo-american/aal.l))
today noted the announcement by Anglo American Platinum Limited released today to
the Johannesburg stock exchange. The text of the announcement is copied below:

Anglo American Platinum has safely and successfully completed the repair of the 
Anglo Converter Plant (ACP) Phase B unit. The ACP and full downstream processing
operations are completing a safe ramp-up and expect to be fully operational from
12 May 2020. Force majeure to suppliers of concentrate will be lifted on that date.

> **CEO of Anglo American Platinum, Natascha Viljoen, stated:**
> “I am pleased to report that we have safely and successfully completed the repair
> of the ACP Phase B unit ahead of schedule, enabling the restart of refined production
> of our platinum group metals and our base metals. We were vigilant in adhering
> to strict health and safety protocols to keep the repair team safe during the 
> lockdown, whilst ensuring that we were able to implement social distancing and
> hygiene requirements which form our new way of working during the COVID-19 pandemic.
> We have carried out substantial testing to ensure the stability of the ACP Phase
> B unit, and as we complete the ramp-up, we are engaging with suppliers of concentrate
> to lift force majeure imminently. All temporary commercial arrangements applicable
> during the force majeure period will revert to normal commercial terms.”

The estimated final cost of repairs for ACP Phase B is c.R150 million, in line with
the lower end of guidance provided. Repair work on the ACP Phase A unit continues
and is progressing in line with the project plan. All orders for long lead items
have been placed and the dismantling work started on site.

Due to the time taken to refine the respective platinum group and base metals, the
force majeure notice remains in effect for our refined metal customers. Force majeure
arrangements with these customers will be lifted in the future and in line with 
the provisions of our agreements.

Given the collective uncertainty around the start-up of ACP, the ramp-up of mining
operations and the potential impact of COVID-19, Anglo American Platinum retains
its current guidance and will provide an update as appropriate when we have further
information and clarity on production.

**A safe and successful repair under lockdown**

In accordance with lockdown regulations, the repair team was able to continue with
repairs throughout the extended lockdown period in South Africa. All materials required
for repairs were ordered and available on site ahead of the lockdown, and there 
were no supply chain disruptions that impacted the ability to complete the repairs.
Safety protocols were implemented on site in line with Government approvals and 
regulations. A construction work risk review was completed to determine work phasing,
method of execution, key resource identification and increased health protocols.

The ACP construction repair team was split into two teams that self-isolated for
the duration of the repair work, and COVID-19 specific health protocols were put
in place for cleaning, screening and transport to site. A new shift pattern was 
introduced that fostered social distancing. Increased site hygiene measures for 
sanitisation, together with site safety and health supervision were implemented 
to ensure safety and quality of construction. We have reported zero injuries, zero
health issues or positive COVID-19 cases and did not experience any health and safety
or construction issues during the repair and ramp up.

Anglo American’s ability to continue these essential repairs during lockdown has
been critical to the resumption of the processing pipeline. As a result of the incidents
at the ACP, and the need to shut operations to secure a safe operational environment
for employees, the Company could not process any metal to final product during this
period. With mining activity resuming to varying degrees under the current Level
4 lockdown restrictions, the Company is now able to begin processing concentrate
and releasing metal from the pipeline.