**Amaroq Ltd** (LON:AMRQ, TSX-V, NASDAQ Iceland: AMRQ, OTCQX: AMRQF), an independent
mine development corporation focused on unlocking Greenland’s mineral potential,
has announced its Q2 2025 Financial Results. All dollar amounts are expressed in
Canadian dollars unless otherwise noted.

A remote presentation for analysts and investors will be held later today at 9:30am
BST, details of which can be found further down in this announcement.

> **Eldur Olafsson, CEO of Amaroq, commented:**
> _“I am pleased to report good progress across __all of__ the commissioning activities
> at our __Nalunaq__ mine, as we continued the trial mining, on-going construction
> and commissioning of the processing plant, development of essential infrastructure,
> as well as stabilization of process plant operating activities. By the end of 
> Q2-25__,__ we had reached two significant milestones, with the __first __shipment
> and export of gold __doré__ bars and __the associated __maiden revenue from operations
> of __C$__3.4__ million__. __In terms of commissionin__g progress, __I am very 
> encouraged that in Q2-25__,__ we achieved an average of 3.6x more processing throughput
> __versus__ Q1-25 and mining ore production was 2.6x better in Q2-25 versus Q1-
> 25__._ _I am__ pleased to note that this trend has continued in the third quarter__,
> with a further 36kg of __doré__ bars in the safe at site__,__ at the time of writing._
> _“__In June 2025, we successfully completed a__n oversubscribed and upsized__ 
> £45 million __equity __fundraise, following significant reverse interest from__
> international__ institutional investors__. Alongside the fundraise we__ announced
> the acquisition of the West Greenland Hub, a new mining province for the Company
> in Greenland. The West Greenland Hub contains the __previously producing Black
> Angel mine__ and __Kangerluarsuk__ licences and crystallises our position as the
> largest acreage holder in Greenland, as well as geographically diversifying our
> operations into this highly prospective new area in the __north west__ of Greenland._
> _“__With good commissioning progress to date__,__ coupled with the flexibility
> provided by the enhanced liquidity position __following the upsized fundraise__;
> __ management have decided to bring forward certain construction and commissioning
> activities for the installation of the flotation recovery (Phase 2) systems__,
> __ into __Q3 and Q4__ 2025. This will require a period of shut down at the processing
> facility to accommodate these activities__ but will enable __critical__ work to
> be completed before __w__inter__,__ when operating conditions are more challenging__,
> however mining will continue as normal__. __Once completed, the processing facility
> will be calibrated to higher recovery rates, enabling higher cash generation from
> the facility, which will be further enhanced once it is running at __the nameplate
> throughput of 300 t/d, which remains our target by year end 2025. __The __additional
> __proposed construction and commissioning activities in Q3 and Q4-25 means we 
> are ta__rgeting __production for__ the yea__r__ of approximately 5koz__ of gold__
> for the full year 2025._
> _“__During the Period, we also completed the planning and scheduling for all __o__f
> our seasonal exploration field work activities across the gold and strategic mineral
> asset base, this includes a __comprehensive, multi-rig drilling programme __at
> __Nalunaq__, targeting continued resource expansion, with up to 3,500 metres of
> surface drilling and near-continuous underground drilling planned, as well as 
> at Nanoq, the analogous gold prospect east of __Nalunaq__ within the __Nanortalik__
> gold belt, with approximately 5,000 metres of core drilling to advance towards
> a maiden Mineral Resource Estimate, as well as operations to expand our understanding
> across existing and new satellite gold targets within the __Nanortalik__ gold 
> belt__.__”_

**Q2**** 2025 Corporate Highlights**

 * Maiden revenue of $3.4 million in Q2 2025, following the first commercial sale
   of gold doré bars from the Nalunaq mine.
 * Successfully completed an oversubscribed and upsized equity fundraise in June
   2025, raising gross proceeds of approximately £45.0 million.
    - In June 2025, Amaroq announced the proposed acquisitions of the past producing
      Black Angel mine and Kangerluarsuk licences to create a West Greenland Hub.
    - In May 2025, Amaroq signed a non-binding heads of terms with JLE Group Ltd
      to establish a special purpose vehicle and create a joint venture company 
      to be called Suliaq ApS, dedicated to the provision of essential services,
      supplies and supporting assets to Greenland’s growing mining sector and wider
      economy.
    - Amaroq group liquidity of $75.0 million, at period end, consisting of cash
      balances of $86.0 million, an undrawn revolving credit facility of $8.9 million
      less trade payables of $19.8 million ($23.4 million as at 31 March 2025).

**Q****2**** 2025 Operational Highlights**

 * Completion of first commercial shipments and export of doré bars containing 808
   ounces of gold.
 * Gold doré bars containing 724 ounces of gold were shipped to a refinery facility
   in Switzerland, and subsequently sold to Auramet for gross proceeds of $[3.4]
   million.
 * The Company further shipped 84 ounces of gold to a specialised refinery in the
   UK for further refining and accreditation as Single Mine Origin (“SMO”) gold,
   which will be available for purchase by the local Greenlandic population and 
   jewellery makers.
 * In May 2025, Amaroq announced the results of its successful 2024 exploration 
   results across the Company’s strategic minerals portfolio JV, Gardaq AS.
 * Operations at Nalunaq continue to ramp up and remain on track to reach nameplate
   processing capacity of 300 t/d by the end of the year.

**Commissioning and Outlook Highlights**

 * Significant operational progress throughout Q2-25 has continued into Q3-25.
 * With continued up-time in mine development rates and processing throughput of
   ~145 t/d in July 2025 on a single shift due to continued construction and commissioning
   work, the Company continues to target a run rate production of 300 t/d by the
   end of 2025.
 * Enhanced liquidity post fundraise has enabled the Company to bring forward certain
   construction and commissioning activities for the installation of flotation recovery(
   Phase 2) into the third quarter of 2025, which will require a short period of
   shut down at the processing facility, however mining will continue as normal.
 * Once these activities are completed the processing facility will be calibrated
   to higher recovery rates, enabling higher cash generation from the facility, 
   which will be further enhanced once it is running at nameplate throughput of 
   300 t/d.
 * As a result of having the flexibility to bring forward this Phase 2 work, and
   the subsequent period of shut down, the Company is targeting full year production
   of approximately 5koz for the full year 2025.

**Post Period ****Corporate ****Highlights**

 * On 1 July 2025, Amaroq commenced trading on the OTCQX, enabling higher transparency
   and trading opportunities for investors in the U.S.
 * In July 2025, Amaroq commenced its 2025 exploration campaign, one of the most
   ambitious and wide-ranging programs in Amaroq’s history.
 * On 15 July 2025, the Company changed its name from “Amaroq Minerals Ltd.” to “
   Amaroq Ltd.”
 * At Nanoq, a large multi-rig programme was mobilised post period end, with operations
   commencing in August 2025. This programme will include the construction of a 
   ~40-person camp.
 * Post period, Amaroq published its inaugural [Sustainability](https://www.directorstalkinterviews.com/sustainability-green-stocks-news)
   Report, highlighting the Company’s commitment to responsible development across
   four key areas: corporate governance, our environment, our people, and our community.
   The report is available on the Company’s website at https://www.amaroqminerals.
   com/responsibility/#tab-sustainabilityreport .

**Services and Renewable Energy business lines**
Alongside the Company’s focus on
its two key pillars of mining development and exploration, below is an update on
the two mining associated business units:

 * Suliaq ApS – During Q2-25, the Company incorporated a subsidiary entity called
   Suliaq ApS in order to create a standalone business which will look to take advantage
   of the increased interest in mining and infrastructure in Greenland, through 
   the provision of Amaroq’s equipment and services, generating additional revenue.
   In addition, on 28 May 2025, the Company signed a non-binding head of terms with
   JLE, whereby JLE will invest £4.0 million, by way of an equity contribution in
   exchange for a 10% shareholding in the subsidiary company, with Amaroq holding
   90%. JLE has the option to increase its investment up to a total of £12.0 million,
   structured in additional tranches of £4.0 million, which will result in proportional
   increases in JLE’s equity stake in the company. During the second half of 2025
   a Board and management team will be put in place and initial contracts for the
   rental of equipment and services to third parties and other companies controlled
   by the Company, will be finalised.
 * Renewable energy generation – Power generation and energy provision are some 
   of the most expensive and polluting cost items within remote mining operations.
   To de-risk the future life of mine at Nalunaq, whilst at the same time investing
   in technologies to power the future mines, the Corporation is in advanced plans
   for the construction of at least one mega watt (“MW”) of hydro power, within 
   close proximity of Nalunaq. During the second half of 2025, following the request
   for the trial pit investigation licence in July 2025, designs will be finalised
   and tenders for turbine, generator, transformer, powerhouse & penstock will be
   solicited, ahead of the publication of the prefeasibility report and application
   for the project to take place within the existing Nalunaq Mine Plan framework
   by the end of 2025, allowing for construction and power generation in 2026. It
   is anticipated that by year end 2025, the hydro electric business will be formally
   incorporated in Greenland, under the name IMEQ ApS.

**Strategic Acquisitions and West Greenland Hub**
Further to the announcement on
11 June 2025, the Company has signed the asset purchase agreement for the acquisition
of the Kangerluarsuk licences from 80 Mile plc (and Disko Exploration Ltd). Preparations
for completion are underway. For the Black Angel transaction with FBC Mining (BA)
Limited, which includes the former producing mine and associated infrastructure,
the parties are progressing the agreed conditions precedent. On completion, these
acquisitions will form the West Greenland Hub as previously outlined.

**Update on Impact Benefit Agreement**
Additionally, the Company provides an update
on the progress of the Impact Benefit Agreement (IBA).

Amaroq has been actively working in collaboration with the Government of Greenland
and Kommune Kujalleq to advance the IBA. However, due to the Government of Greenland’s
need to address competing priorities, and in recognition of these circumstances,
an extension of the deadline to 31 December 2025 has been agreed. Amaroq remains
fully committed to its collaborative approach to ensure the IBA reflects the shared
objectives of all parties. This delay to the formalization of the IBA will not impact
current and future operations.

**Details of conference call**
A conference call for analysts and investors will
be held this morning at 9:30am BST, including a management presentation and Q&A 
session.