**Amaroq Ltd. **(LON:AMRQ, NASDAQ Iceland: AMRQ, OTCQX: AMRQF), an independent mine
development company focused on unlocking Greenland’s mineral potential, has announced
its Q1 2026 Financial Results. All dollar amounts are expressed in Canadian dollars
unless otherwise noted.

The Company will be hosting a Capital Markets Update later today at 14:30 BST, details
of which can be found further down in this announcement.

> **Eldur Olafsson, CEO of Amaroq, commented:** _“I am pleased to report a strong
> first quarter’s operational and financial performance, in line with expectations
> and guidance for the full year. Mining operations and processing at the Nalunaq
> gold mine performed well, with gold grades and recoveries very much in line with
> guidance._
> _“With the completion of Phase 1 commissioning, we continued to ramp up mining
> and milling rates through the quarter and successfully navigated the challenging
> winter month personnel rotations. Current trading has been strong, keeping us 
> on track for the H1 2026 guidance of 7 to 10koz of gold and full year of 25 to
> 35k oz. I am also excited that we will be kicking off our high impact 2026 exploration
> campaign in June 2026, starting at the Ilua Rare Earth prospect._
> _“In addition, today we are hosting a capital markets update in London, showcasing
> the extensive growth pipeline we are looking to unlock over the next five years,
> as well as a deeper look into the Nalunaq gold mine and its own resource and production
> growth potential; highlighting the significant latent value we have within the
> business ready to be realised. Amaroq has started 2026 in a very strong position
> and I look forward to updating the market as this year progresses.”_

**Q1 2026 Financial Highlights – ****_in line with management expectations and budget_**

 * Revenue of $18.9 million (Q1 2025: $0m) from total gold sales of 2,970 oz at 
   an average gold price of USD 4,656/oz.
 * Gross profit of $9.8 million and net profit of $2.4 million.
 * Capital assets of $275.4 million as at March 31, 2026 ($252.7 million as at December
   31, 2025).
 * Gold inventory of $20.3 million as at March 31, 2026 ($15.8 million as at December
   31, 2025).
 * Cash balance of $8.8 million as at March 31, 2026 ($21.5 million as at December
   31, 2025).

**Q1 2026 Operational Highlights ****_– In line with production guidance and higher
than anticipated grade_**

 * Nalunaq produced a total of 3,694oz of gold, in line with guidance with average
   feed grade of 19.9 g/t, which is higher than 2026 guidance of 14 to 15 g/t, as
   reconciliation against the 2026 mine plan showed improvements.
 * Average recoveries were 61%, in line with the planned recovery factor for Phase
   1 of ~60%.
 * On January 8, 2026, the Company announced the award of the Final Impact Benefit
   Agreement for the Nalunaq gold mine.
 * On January 21, 2026, the Company announced exploration results from the 2025 
   field campaign at its Minturn IOCG prospect; identifying high-grade iron assays
   from surface samples, including iron grades up to 69.5% Fe, underscoring the 
   presence of a significant iron-oxide core within the system.
 * On March 20, 2026, the Company received the signed approval of the Final Mine
   Plan and Closure Plan for the Nalunaq Licence from the Government of Greenland.
 * Post-period, on April 30, 2026, Amaroq secured a Revolving Credit Facility (RCF)
   with Landsbankinn and Gunvor Group with increased capacity of US$70 million, 
   replacing its existing US$35 million RCF while reducing the overall cost of funding.

**Corporate**

 * On February 18, 2026, the Company reiterated its intention to upgrade its London
   Stock Exchange listing to the Main Market, appointing Citigroup Global Markets
   Limited to act as sponsor and financial adviser.
 * On March 19, 2026, the Company completed the voluntary delisting of its common
   shares from the TSX Venture Exchange (the “TSXV”).

**2026 guidance vs actual performance table:**

|   | **Guidance for FY 2026** | **Q1 2026 actuals** | 
| 2026 gold production | 25 to 35koz | 3.7koz | 
| Average feed grade (g/t) | 14 to 15 g/t | 19.9 g/t | 
| Gravity recovery (%) | 50-70% | 61% | 
| Nalunaq cash cost | USD44 to 47m | USD9.8m | 
| Nalunaq AISC | USD69 to 73m | USD16.7m |

**Outlook**

 * The Company reiterates FY2026 gold production guidance of 25-35 koz and confirms
   current trading in line with this range, with production expected to be weighted
   towards the second half of 2026, following commissioning of the flotation circuit.
 * The 2026 exploration campaign will commence in June 2026 at the Ilua REE prospect,
   with the aim of further delineating the scale of the REE hosting pegmatite systems
   and to conduct initial scout drilling to understand depth potential and volumetrics.
 * Other exploration activities include:
    - July 2026 – Rehabilitation of surface facilities, updating of studies and 
      commencing resource growth exploration at Black Angel, the previously producing
      zinc, lead, silver, germanium and gallium mine acquired in 2025, targeting
      drilling in 2026 and/or 2027.
    - July 2026 – Conduct surface geophysical work and a scout drilling programme,
      at the large Minturn IOCG prospect, to assess the scale of the mineralisation
      and potential economics of the target.
    - July/August 2026 – Systematic drill testing of the Central Zone at the Nanoq
      future gold project, in the southern Greenland Nanortalik gold belt with the
      objective of establishing the geological continuity and data density required
      to underpin a Maiden Mineral Resource Estimate.
    - August 2026 – The Company will continue to develop additional drill sites 
      at the Stendalen copper nickel prospect, targeting potential sulphide traps
      and is reviewing options to action these during the upcoming season.
 * The Company continues to make good progress on the transition to the Main Market
   of the London Stock Exchange in 2026.

**Nalunaq Operations Overview**
Following the transition to a fully owner-operated
mining model, the Company has invested in its own underground mining fleet, which
had been largely delivered and commissioned by the end of Q1 2026.

During the first quarter, 33,404t of material was mined, equivalent to 11,120t of
ore. Development continued in the Mountain Block, with the main ramp approaching
the 816 metre level. While commissioning of the flotation circuit remains on schedule
for Q2 2026, gold-bearing tailings are currently being transported back to the mine
and stockpiled for reintroduction into the processing plant, once the flotation 
circuit becomes operational.

During the quarter, a total of 12,032t of material was processed at an average mill
feed grade of 19.9g/t gold. Gold production totalled 3,694oz, while sales amounted
to 2,970oz of gold. The average realised gold price during the quarter was US$4,656/
oz.

Gold production for 2026 is guided at 25 to 35 koz, with production expected to 
be weighted towards the second half of 2026, following commissioning of the flotation
circuit, which is anticipated to increase overall gold recoveries from a range of
50–70%, under the current gravity-only circuit, to approximately 90–95%.

**Exploration Overview**
**Gold Exploration Projects in Q1 2026**At Nalunaq, a total
of 2,411.5m from 31 underground drillholes have been completed during the first 
quarter, providing support to short and medium term mine planning. Alongside Bara
Consulting, the Company has been reviewing all results up to the end of 2025 to 
allow the update of the current Mineral Resource estimate (MRE4).

With assistance from SRK Consulting UK, Amaroq has been reviewing geological modelling
at Nanoq allowing for 2026 programme design, as well as initial Mineral Resource
Estimate. A metallurgical sample exceeding 100 kg has been dispatched to SGS Lakefield,
Canada, to support initial test work assessing anticipated processing performance
and recovery characteristics. Design work relating to potential 2026 exploration
programmes has continued alongside ongoing geological reviews within the broader
Nanortalik Gold Belt.

**Strategic Minerals Projects in Q1 2026 (51% ownership through Gardaq Joint Venture)**

The 2026 field season options for Stendalen have been designed alongside assessment
of logistical requirements. A review of the 2025 exploration results for Ilua, and
in particular the REE hosting mineralogy has been commenced alongside the University
of St Andrews, ahead of implementation of the 2026 programme.

The Company continues to review the geological data for the large IOCG prospect 
Minturn, to build a robust 2026 field programme. Results from across the wider South
Greenland Copper Belt continued to be reviewed and evaluated during the reporting
period.

**West Greenland Hub**
In Q1 2026 at Black Angel, Amaroq continued discussions with
various contractors and consultants regarding the refurbishment of infrastructure,
planning and logistical preparation for the 2026 field season, and the review and
updating of historical technical studies. Design options for a 2026 and/or 2027 
drilling campaign at Kangerluarsuk have been reviewed and are under assessment.

**Capital Markets Update**
The Company will be hosting a Capital Markets Update 
for investors and analysts at 14:30 BST today. The event will be held in London 
and available via live webcast. A recording of the presentation will be made available
on the Company’s website following the event.

To register for the webcast, please enter your details via the following link: https://
edge.media-server.com/mmc/p/h5ac64dd

There is no new or price sensitive information being provided as part of the presentation.
The presentation itself will be available on the Company’s website from 1300 BST
today, link: [Presentations – Amaroq Ltd.](https://www.globenewswire.com/Tracker?data=88PVHYBcsZ0lnS4LTPDXV8XEeEoRdoY-oziainDAOeaYwVUFSI8zSjQnAnZ0C4bB997mMLWGQlT170nB3q0pi1j7E4TLmr6rCkmTKj8Auhb-ZqGgPxwLnI1uPxOpfCZNx9JCPUzuUE_wgamQnVcZAw==)

**Financial Results**

| **Period ended March 31, 2026** |   | **Three months** |   | **Three months** | 
|   |   | **2026** |   | **2025** | 
|   |   | $ |   | $ | 
| **Financial Results** |   |   |   |   | 
| Revenue |   | 18,945,404 |   | – | 
| Cost of Sales |   | (8,584,102) |   | – | 
| Selling, refining and royalty costs |   | (493,975) |   | – | 
| Exploration and evaluation expenses |   | (401,567) |   | (193,420) | 
| General and administrative expenses |   | (5,794,031) |   | (4,581,116) | 
| Depreciation and amortization |   | (270,114) |   | (45,205) | 
| Selling expenses |   | – |   | (48,352) | 
| Foreign exchange gain (loss) |   | (737,939) |   | 591,610 | 
| Interest income |   | 149,334 |   | 26,306 | 
| Gardaq project management fees |   | 613,613 |   | 643,553 | 
| Gain on lease modification |   | – |   | 30,543 | 
| Loss on loan modification |   | (271,437) |   | – | 
| Share of net losses of joint arrangement |   | (376,680) |   | (370,343) | 
| Finance costs |   | (330,477) |   | (452,273) | 
| Net income (loss) and comprehensive income (loss) |   | 2,448,029 |   | (4,398,697) | 
| Basic earnings (loss) per common share |   | 0.005 |   | (0.011) | 
| Diluted earnings (loss) per common share |   | 0.005 |   | (0.011) |

**Financial Position**

| **Financial Position** | **As at** | 
|   | **March 31, 2026** | **March 31, 2025** | 
|   | $ | $ | 
| **Financial Position** |   |   | 
| Cash | 8,772,700 | 16,698,642 | 
| Investment in equity-accounted joint arrangement | 12,400,944 | 14,531,970 | 
| Total assets | 375,589,106 | 252,074,553 | 
| Total current liabilities | 33,638,679 | 46,894,778     | 
| Total non-current liabilities | 59,085,389 | 7,641,551 | 
| Shareholders’ equity | 282,865,038 | 197,538,224 | 
| Working capital (before loan payable)^(1) | 24,252,228 | 22,238,142    | 
| Working capital (loan payable included)^( 1) | 24,252,228 | (7,563,780) |